Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2026-07-03
- Hijri
- 18 Muharram 1448 AH
- Reference
- PAY-2025-025-05
Interim payment certificate no. (5)
For the work of June 2026
- Contract number
- SCA/2025/025
- Etimad reference
- 2504860719
- Contract
- Arar vocational qualification centre — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Arar Vocational Qualification Centre
- Contract period
- 2025-08-03 — 2027-08-31
- Original contract value
- 196,000,000
- Current contract value
- 196,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 56,670,000 |
| 2 | Less: previous certificates | (45,320,000) |
| 3 | Value of work in this certificate | 11,350,000 |
| 4 | Less: retention (10%) | (1,135,000) |
| 5 | Less: advance payment recovery (10%) | (1,135,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,270,000) |
| 8 | Net before VAT | 9,080,000 |
| 9 | Add: value added tax (15%) | 1,362,000 |
| 10 | Net amount payable to the contractor | 10,442,000 |
Amount in words: Ten million four hundred forty-two thousand Saudi riyals only
Retention held up to this certificate: SAR 5.7M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 13,720,000 | 7,477,000 | 1,675,000 | 9,152,000 | 67% |
| Earthworks & foundations | 35,280,000 | 11,602,000 | 2,679,000 | 14,281,000 | 40% |
| Concrete & structural works | 60,760,000 | 15,436,000 | 3,888,000 | 19,324,000 | 32% |
| Mechanical, electrical & plumbing | 47,040,000 | 7,433,000 | 2,088,000 | 9,521,000 | 20% |
| Finishes & external works | 29,400,000 | 2,943,000 | 882,000 | 3,825,000 | 13% |
| Testing & commissioning | 9,800,000 | 429,000 | 138,000 | 567,000 | 6% |
| Total | 196,000,000 | 45,320,000 | 11,350,000 | 56,670,000 | 29% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ibrahim A. Al-Ghamdi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani