Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2026-09-13
- Hijri
- 2 Rabiʻ II 1448 AH
- Reference
- PAY-2025-025-06
Interim payment certificate no. (6)
For the work of August 2026
- Contract number
- SCA/2025/025
- Etimad reference
- 2504860719
- Contract
- Arar vocational qualification centre — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Arar Vocational Qualification Centre
- Contract period
- 2025-08-03 — 2027-08-31
- Original contract value
- 196,000,000
- Current contract value
- 196,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 62,700,000 |
| 2 | Less: previous certificates | (56,670,000) |
| 3 | Value of work in this certificate | 6,030,000 |
| 4 | Less: retention (10%) | (603,000) |
| 5 | Less: advance payment recovery (10%) | (603,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,206,000) |
| 8 | Net before VAT | 4,824,000 |
| 9 | Add: value added tax (15%) | 723,600 |
| 10 | Net amount payable to the contractor | 5,547,600 |
Amount in words: Five million five hundred forty-seven thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 6.3M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 13,720,000 | 9,247,000 | 879,000 | 10,126,000 | 74% |
| Earthworks & foundations | 35,280,000 | 14,390,000 | 1,410,000 | 15,800,000 | 45% |
| Concrete & structural works | 60,760,000 | 19,314,000 | 2,067,000 | 21,381,000 | 35% |
| Mechanical, electrical & plumbing | 47,040,000 | 9,411,000 | 1,123,000 | 10,534,000 | 22% |
| Finishes & external works | 29,400,000 | 3,755,000 | 477,000 | 4,232,000 | 14% |
| Testing & commissioning | 9,800,000 | 553,000 | 74,000 | 627,000 | 6% |
| Total | 196,000,000 | 56,670,000 | 6,030,000 | 62,700,000 | 32% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ibrahim A. Al-Ghamdi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani