DMD-2026-005

Redesigning contractor waiting areas in the existing branches

PrioritizedDevelopment proposal
Electronic formPriority evaluation
Priority score
63

Score confirmed by the evaluation panel

Estimated cost
SAR 38M
Net present value
SAR 5.2M
Internal rate of return
⁦9.6%⁩
Payback period
⁦5.5⁩ years
Rank in the 2027 plan
#8

of ⁦9⁩ candidates

  1. Gate into «Submitted»DecisionGoDate15 April 2026DraftComplete
  2. Gate into «Initial review»DecisionGoDate13 May 2026SubmittedComplete
  3. Gate into «Feasibility»DecisionGoDate9 June 2026Initial reviewComplete
  4. Gate into «Evaluation»DecisionGoDate7 July 2026FeasibilityComplete
  5. Gate into «Committee review»DecisionGoDate4 August 2026EvaluationComplete
  6. Gate into «Approved»DecisionConditional goDate31 August 20262 open conditionsCommittee reviewComplete
  7. Gate into «Prioritized»DecisionGoDate28 September 2026ApprovedComplete
  8. Gate into «Converted to project»DecisionNot held yetPrioritizedCurrent stageCurrent stage
  9. 9Converted to projectNot started

The request as filed

What the requester wrote on the intake form

Problem
Branch managers in Riyadh, Jeddah and Al-Khobar report crowded reception areas on skills-test days — contractors and trainees wait in the corridors outside the halls — and 140 formal complaints were logged in 2025.
Current state
Reception areas in the existing branches hold only 40% of peak attendance, with no calling screens or service desks near the halls.
Objective
Redesign contractor waiting areas in 14 existing branches and centres with proper halls and calling screens tied to the test and appointment schedules by 2029.
Expected scope
Design and build of the waiting areas, furniture and wayfinding, calling screens, contractor service desks near the halls, and access for people with disabilities.

Expected benefits

Customer satisfaction

Contractor satisfaction with branch service up 6 points

Time & speed

Waiting time before an appointment or test down 40%

Productivity

Tests start on time with electronic calling

Strategic link

The objectives it serves and how well it aligns

Strategic alignment · Good

Related lessons learned

From similar past projects — read them before evaluation

Loose scope in design-build contracts breeds claims

From SCA Academy Campus, Riyadh

The contractor claimed SAR 14M for requirements added after concept design: extra e-test halls and trainers’ offices.

Recommendation: Freeze the building’s functional programme with the sector that will use it before the proposal goes to committee.

Open the lesson