SCA Backup Data Centre Subtask Last item under this branch 2027-01-09 72% SCA Backup Data Centre Planned: 2025-04-06 → 2026-11-30 Forecast: 2025-04-06 → 2027-01-09 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-10-18 100% Management & governance Planned: 2025-04-06 → 2025-08-19 Actual: 2025-04-06 → 2025-10-18
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-08-04 100% Project plan & baseline Planned: 2025-04-06 → 2025-06-28 Actual: 2025-04-06 → 2025-08-04
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-10-18 100% Monitoring & reporting Planned: 2025-05-28 → 2025-08-19 Actual: 2025-06-20 → 2025-10-18
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-10-18 100% Project plan approved Planned: 2025-08-19 → 2025-08-19 Actual: 2025-10-18 → 2025-10-18 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-03-17 100% Analysis & design Planned: 2025-07-19 → 2025-12-01 Actual: 2025-09-03 → 2026-03-17
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-01 100% Business requirements Planned: 2025-07-19 → 2025-10-10 Actual: 2025-09-03 → 2026-01-01
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-17 100% Solution design Planned: 2025-09-09 → 2025-12-01 Actual: 2025-11-17 → 2026-03-17
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-17 100% Designs approved Planned: 2025-12-01 → 2025-12-01 Actual: 2026-03-17 → 2026-03-17 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-10-26 100% Build Planned: 2025-10-31 → 2026-05-06 Actual: 2026-01-31 → 2026-10-26
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-31 100% Release 1 Planned: 2025-10-31 → 2026-01-22 Actual: 2026-01-31 → 2026-05-31
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-14 100% Release 2 Planned: 2025-12-22 → 2026-03-15 Actual: 2026-04-16 → 2026-08-14
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Integrations Planned: 2026-02-12 → 2026-05-06 Actual: 2026-06-30 → 2026-10-26
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Build complete Planned: 2026-05-06 → 2026-05-06 Actual: 2026-10-26 → 2026-10-26 Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-12-08 35% Testing & acceptance Planned: 2026-04-05 → 2026-08-18 Forecast: 2026-04-05 → 2026-12-08 Float: 0d
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-22 70% System testing Planned: 2026-04-05 → 2026-06-27 Forecast: 2026-04-05 → 2026-11-22 Float: 0d Drag to change its duration +148
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-08 0% User acceptance testing Planned: 2026-05-27 → 2026-08-18 Forecast: 2026-11-13 → 2026-12-08 Float: 0d Drag to change its dates +112
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-08 0% Testing & acceptance complete Planned: 2026-08-18 → 2026-08-18 Forecast: 2026-12-08 → 2026-12-08 Float: 32d Drag to change its dates Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-09 0% Launch & handover Planned: 2026-07-18 → 2026-11-30 Forecast: 2026-11-29 → 2027-01-09 Float: 0d
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-24 0% Training & change Planned: 2026-07-18 → 2026-10-09 Forecast: 2026-11-29 → 2026-12-24 Float: 0d Drag to change its dates +76
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-09 0% Go-live & handover Planned: 2026-09-08 → 2026-11-30 Forecast: 2026-12-15 → 2027-01-09 Float: 0d Drag to change its dates +40
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-09 0% Final handover Planned: 2026-11-30 → 2026-11-30 Forecast: 2027-01-09 → 2027-01-09 Float: 0d Drag to change its dates Final handover