Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-10-13
- Hijri
- 21 Rabiʻ II 1447 AH
- Reference
- PAY-2025-012-03
Interim payment certificate no. (3)
For the work of September 2025
- Contract number
- SCA/2025/012
- Etimad reference
- 2503950550
- Contract
- Network & server equipment — backup data centre
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- SCA Backup Data Centre
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 38,000,000
- Current contract value
- 38,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 4,980,000 |
| 2 | Less: previous certificates | (2,940,000) |
| 3 | Value of work in this certificate | 2,040,000 |
| 4 | Less: retention (5%) | (102,000) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (102,000) |
| 8 | Net before VAT | 1,938,000 |
| 9 | Add: value added tax (15%) | 290,700 |
| 10 | Net amount payable to the contractor | 2,228,700 |
Amount in words: Two million two hundred twenty-eight thousand seven hundred Saudi riyals only
Retention held up to this certificate: SAR 249K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,660,000 | 486,000 | 318,000 | 804,000 | 30% |
| Earthworks & foundations | 6,840,000 | 754,000 | 501,000 | 1,255,000 | 18% |
| Concrete & structural works | 11,780,000 | 1,001,000 | 697,000 | 1,698,000 | 14% |
| Mechanical, electrical & plumbing | 9,120,000 | 481,000 | 356,000 | 837,000 | 9% |
| Finishes & external works | 5,700,000 | 190,000 | 146,000 | 336,000 | 6% |
| Testing & commissioning | 1,900,000 | 28,000 | 22,000 | 50,000 | 3% |
| Total | 38,000,000 | 2,940,000 | 2,040,000 | 4,980,000 | 13% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani