Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 11
- Date
- 2026-10-06
- Hijri
- 25 Rabiʻ II 1448 AH
- Reference
- PAY-2025-012-11
Interim payment certificate no. (11)
For the work of September 2026
- Contract number
- SCA/2025/012
- Etimad reference
- 2503950550
- Contract
- Network & server equipment — backup data centre
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- SCA Backup Data Centre
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 38,000,000
- Current contract value
- 38,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 24,500,000 |
| 2 | Less: previous certificates | (23,440,000) |
| 3 | Value of work in this certificate | 1,060,000 |
| 4 | Less: retention (5%) | (53,000) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (53,000) |
| 8 | Net before VAT | 1,007,000 |
| 9 | Add: value added tax (15%) | 151,050 |
| 10 | Net amount payable to the contractor | 1,158,050 |
Amount in words: One million one hundred fifty-eight thousand fifty Saudi riyals only
Retention held up to this certificate: SAR 1.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,660,000 | 2,578,000 | 82,000 | 2,660,000 | 100% |
| Earthworks & foundations | 6,840,000 | 6,607,000 | 233,000 | 6,840,000 | 100% |
| Concrete & structural works | 11,780,000 | 8,594,000 | 391,000 | 8,985,000 | 76% |
| Mechanical, electrical & plumbing | 9,120,000 | 3,885,000 | 231,000 | 4,116,000 | 45% |
| Finishes & external works | 5,700,000 | 1,548,000 | 106,000 | 1,654,000 | 29% |
| Testing & commissioning | 1,900,000 | 228,000 | 17,000 | 245,000 | 13% |
| Total | 38,000,000 | 23,440,000 | 1,060,000 | 24,500,000 | 64% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani