SCA/2025/012
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
64% of the current value paid
Paid
24.5Mof a current value of SAR 38M
Value of each certificate
The last 11 — gross and net
Approved: 11
Count: 11 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 11September 2026 | 2026-10-06 | 1.1M | 53K | 0 | 151.1K | 1.2M | Approved | |
| Certificate 10August 2026 | 2026-08-22 | 1.9M | 93K | 0 | 265.1K | 2M | Approved | |
| Certificate 9June 2026 | 2026-07-09 | 2.2M | 108.5K | 0 | 309.2K | 2.4M | Approved | |
| Certificate 8May 2026 | 2026-05-25 | 2.6M | 128.5K | 0 | 366.2K | 2.8M | Approved | |
| Certificate 7March 2026 | 2026-04-10 | 3.3M | 162.5K | 0 | 463.1K | 3.6M | Approved | |
| Certificate 6February 2026 | 2026-02-25 | 2.7M | 137K | 0 | 390.5K | 3M | Approved | |
| Certificate 5December 2025 | 2026-01-11 | 3M | 151K | 0 | 430.4K | 3.3M | Approved | |
| Certificate 4November 2025 | 2025-11-27 | 2.9M | 142.5K | 0 | 406.1K | 3.1M | Approved | |
| Certificate 3September 2025 | 2025-10-13 | 2M | 102K | 0 | 290.7K | 2.2M | Approved | |
| Certificate 2August 2025 | 2025-08-30 | 1.8M | 91.5K | 0 | 260.8K | 2M | Approved | |
| Certificate 1June 2025 | 2025-07-16 | 1.1M | 55.5K | 0 | 158.2K | 1.2M | Approved |