Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2026-02-25
- Hijri
- 8 Ramadan 1447 AH
- Reference
- PAY-2025-012-06
Interim payment certificate no. (6)
For the work of February 2026
- Contract number
- SCA/2025/012
- Etimad reference
- 2503950550
- Contract
- Network & server equipment — backup data centre
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- SCA Backup Data Centre
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 38,000,000
- Current contract value
- 38,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 13,590,000 |
| 2 | Less: previous certificates | (10,850,000) |
| 3 | Value of work in this certificate | 2,740,000 |
| 4 | Less: retention (5%) | (137,000) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (137,000) |
| 8 | Net before VAT | 2,603,000 |
| 9 | Add: value added tax (15%) | 390,450 |
| 10 | Net amount payable to the contractor | 2,993,450 |
Amount in words: Two million nine hundred ninety-three thousand four hundred fifty Saudi riyals only
Retention held up to this certificate: SAR 679.5K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,660,000 | 1,803,000 | 392,000 | 2,195,000 | 83% |
| Earthworks & foundations | 6,840,000 | 2,792,000 | 633,000 | 3,425,000 | 50% |
| Concrete & structural works | 11,780,000 | 3,694,000 | 940,000 | 4,634,000 | 39% |
| Mechanical, electrical & plumbing | 9,120,000 | 1,765,000 | 518,000 | 2,283,000 | 25% |
| Finishes & external works | 5,700,000 | 695,000 | 222,000 | 917,000 | 16% |
| Testing & commissioning | 1,900,000 | 101,000 | 35,000 | 136,000 | 7% |
| Total | 38,000,000 | 10,850,000 | 2,740,000 | 13,590,000 | 36% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani