Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 8
- Date
- 2026-05-25
- Hijri
- 8 Dhuʻl-Hijjah 1447 AH
- Reference
- PAY-2025-012-08
Interim payment certificate no. (8)
For the work of May 2026
- Contract number
- SCA/2025/012
- Etimad reference
- 2503950550
- Contract
- Network & server equipment — backup data centre
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- SCA Backup Data Centre
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 38,000,000
- Current contract value
- 38,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 19,410,000 |
| 2 | Less: previous certificates | (16,840,000) |
| 3 | Value of work in this certificate | 2,570,000 |
| 4 | Less: retention (5%) | (128,500) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (128,500) |
| 8 | Net before VAT | 2,441,500 |
| 9 | Add: value added tax (15%) | 366,225 |
| 10 | Net amount payable to the contractor | 2,807,725 |
Amount in words: Two million eight hundred seven thousand seven hundred twenty-five Saudi riyals only
Retention held up to this certificate: SAR 970.5K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,660,000 | 2,375,000 | 285,000 | 2,660,000 | 100% |
| Earthworks & foundations | 6,840,000 | 4,755,000 | 611,000 | 5,366,000 | 78% |
| Concrete & structural works | 11,780,000 | 5,735,000 | 884,000 | 6,619,000 | 56% |
| Mechanical, electrical & plumbing | 9,120,000 | 2,740,000 | 521,000 | 3,261,000 | 36% |
| Finishes & external works | 5,700,000 | 1,079,000 | 231,000 | 1,310,000 | 23% |
| Testing & commissioning | 1,900,000 | 156,000 | 38,000 | 194,000 | 10% |
| Total | 38,000,000 | 16,840,000 | 2,570,000 | 19,410,000 | 51% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani