Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 9
- Date
- 2026-07-09
- Hijri
- 24 Muharram 1448 AH
- Reference
- PAY-2025-012-09
Interim payment certificate no. (9)
For the work of June 2026
- Contract number
- SCA/2025/012
- Etimad reference
- 2503950550
- Contract
- Network & server equipment — backup data centre
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- SCA Backup Data Centre
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 38,000,000
- Current contract value
- 38,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 21,580,000 |
| 2 | Less: previous certificates | (19,410,000) |
| 3 | Value of work in this certificate | 2,170,000 |
| 4 | Less: retention (5%) | (108,500) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (108,500) |
| 8 | Net before VAT | 2,061,500 |
| 9 | Add: value added tax (15%) | 309,225 |
| 10 | Net amount payable to the contractor | 2,370,725 |
Amount in words: Two million three hundred seventy thousand seven hundred twenty-five Saudi riyals only
Retention held up to this certificate: SAR 1.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,660,000 | 2,453,000 | 207,000 | 2,660,000 | 100% |
| Earthworks & foundations | 6,840,000 | 5,738,000 | 525,000 | 6,263,000 | 92% |
| Concrete & structural works | 11,780,000 | 6,612,000 | 747,000 | 7,359,000 | 62% |
| Mechanical, electrical & plumbing | 9,120,000 | 3,171,000 | 454,000 | 3,625,000 | 40% |
| Finishes & external works | 5,700,000 | 1,253,000 | 204,000 | 1,457,000 | 26% |
| Testing & commissioning | 1,900,000 | 183,000 | 33,000 | 216,000 | 11% |
| Total | 38,000,000 | 19,410,000 | 2,170,000 | 21,580,000 | 57% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani