Project status card
28 October 2026 · 17 Jumada I 1448 AH
SCA Headquarters, Riyadh
PRJ-2026-002 · Corporate Support Sector · Strategic · WP-2024-002
- Progress
- 42% / 51%
- SPI · CPI
- 0.82 · 0.93
- Spend
- SAR 532.9M / SAR 1.2B
- Estimate at completion
- SAR 1.3B
Schedule
Planned to date 51%
Forecast finish: 2027-09-1211 Rabiʻ II 1449 AH · 74 days late
SPI0.82Schedule performance index · 0.82CPI0.93Cost performance index · 0.93Health dimensions
Last update: 2026-10-2615 Jumada I 1448 AH · Up to date
Deliverables
5 of 9 due deliverables accepted on time (56%)
Next milestones
- Build complete2027-01-179 Shaʻban 1448 AH
- Testing & acceptance complete2027-06-1914 Muharram 1449 AH
- Final handover2027-09-2928 Rabiʻ II 1449 AH
Top risks
- Steel and concrete price rises driving price-adjustment claims20
- Late handover of the northern plot and utility diversions in zones 3 and 420
- Contractor claim for a 120-day extension with compensation16
- Safety incidents around cranes and deep excavations10
Open impediments
- Excavation clashing with a high-voltage line in zone 4 · Escalated
- Neighbour complaints about traffic diversions around the site · In progress
- Conference & exhibition building designs awaiting approval · Open
Decisions and changes waiting
- Review certificate 28 — SCA headquarters
Copilot summary
The scope holds 1 project with a budget of SAR 1.18B: 0 on track and 1 red or critical. Weighted progress is 42% against 51% planned, spend SAR 532.9M, and EAC SAR 1.27B (SAR 88.8M over).
1 project is more than a month behind baseline; the worst: SCA Headquarters, Riyadh (74 days).