PRJ-2026-002Off track4ExecutionConstruction

SCA Headquarters, Riyadh

Remove from watchlist

A 210,000 m² campus in Al-Malqa housing the Authority’s offices, the contractors’ service hall and the conference & exhibition building in six linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 1.2B

Actual cost

SAR 532.9M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 1.3B

SAR +88.8M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

SCA Headquarters, Riyadh

PRJ-2026-002 · Corporate Support Sector · Strategic · WP-2024-002

Off track4ExecutionProject manager: Eng. Ahmed Y. Asiri · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦42%⁩ / ⁦51%⁩
SPI · CPI
0.82 · 0.93
Spend
SAR 532.9M / SAR 1.2B
Estimate at completion
SAR 1.3B

Schedule

⁦9%⁩ behind⁦42%⁩

Planned to date ⁦51%⁩

Forecast finish: 2027-09-1211 Rabiʻ II 1449 AH · 74 days late

SPI0.82Schedule performance index · 0.82CPI0.93Cost performance index · 0.93

Health dimensions

Off track

Last update: 2026-10-2615 Jumada I 1448 AH · Up to date

Deliverables

⁦5⁩ of ⁦9⁩ due deliverables accepted on time (⁦56%⁩)

Next milestones

  • Build complete2027-01-179 Shaʻban 1448 AH
  • Testing & acceptance complete2027-06-1914 Muharram 1449 AH
  • Final handover2027-09-2928 Rabiʻ II 1449 AH

Top risks

  • Steel and concrete price rises driving price-adjustment claims20
  • Late handover of the northern plot and utility diversions in zones 3 and 420
  • Contractor claim for a 120-day extension with compensation16
  • Safety incidents around cranes and deep excavations10

Open impediments

  • Excavation clashing with a high-voltage line in zone 4 · Escalated
  • Neighbour complaints about traffic diversions around the site · In progress
  • Conference & exhibition building designs awaiting approval · Open

Decisions and changes waiting

  • Review certificate 28 — SCA headquarters

Copilot summary

The scope holds 1 project with a budget of SAR 1.18B: 0 on track and 1 red or critical. Weighted progress is 42% against 51% planned, spend SAR 532.9M, and EAC SAR 1.27B (SAR 88.8M over).

1 project is more than a month behind baseline; the worst: SCA Headquarters, Riyadh (74 days).

Saudi Contractors Authority · prepared by Eng. Ahmed Y. Asiri in MunjazInternal

Status: Off track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close