SCA Headquarters, Riyadh Subtask Last item under this branch 2027-09-29 42% SCA Headquarters, Riyadh Planned: 2024-03-03 → 2027-06-30 Forecast: 2024-03-03 → 2027-09-29 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-05-27 100% Management & governance Planned: 2024-03-03 → 2024-11-09 Actual: 2024-03-03 → 2025-05-27
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-12-05 100% Project plan & baseline Planned: 2024-03-03 → 2024-08-04 Actual: 2024-03-03 → 2024-12-05
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-27 100% Monitoring & reporting Planned: 2024-06-07 → 2024-11-09 Actual: 2024-08-23 → 2025-05-27
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-27 100% Project plan approved Planned: 2024-11-09 → 2024-11-09 Actual: 2025-05-27 → 2025-05-27 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-05-07 100% Design & permits Planned: 2024-09-12 → 2025-05-20 Actual: 2025-02-12 → 2026-05-07
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-11-15 100% Detailed design Planned: 2024-09-12 → 2025-02-13 Actual: 2025-02-12 → 2025-11-15
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-07 100% Permits & approvals Planned: 2024-12-17 → 2025-05-20 Actual: 2025-08-04 → 2026-05-07
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-07 100% Designs approved Planned: 2025-05-20 → 2025-05-20 Actual: 2026-05-07 → 2026-05-07 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-17 63% Civil works Planned: 2025-03-23 → 2026-03-05 Forecast: 2025-06-28 → 2027-01-17 Float: 0d
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-27 100% Site works & excavation Planned: 2025-03-23 → 2025-08-25 Actual: 2026-01-24 → 2026-10-27
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-14 89% Structure Planned: 2025-06-28 → 2025-11-29 Forecast: 2025-06-28 → 2026-11-14 Float: 13d Drag to change its duration +350
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-17 0% Finishes Planned: 2025-10-02 → 2026-03-05 Forecast: 2026-10-28 → 2027-01-17 Float: 0d Drag to change its dates +318
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-17 0% Build complete Planned: 2026-03-05 → 2026-03-05 Forecast: 2027-01-17 → 2027-01-17 Float: 255d Drag to change its dates Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-06-19 0% MEP works Planned: 2026-01-06 → 2026-12-19 Forecast: 2026-12-18 → 2027-06-19 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-09 0% Supply Planned: 2026-01-06 → 2026-06-10 Forecast: 2026-12-18 → 2027-03-09 Float: 0d Drag to change its dates +272
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-29 0% Installation Planned: 2026-04-13 → 2026-09-14 Forecast: 2027-02-07 → 2027-04-29 Float: 0d Drag to change its dates +227
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-19 0% Testing & commissioning Planned: 2026-07-18 → 2026-12-19 Forecast: 2027-03-30 → 2027-06-19 Float: 0d Drag to change its dates +182
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-19 0% Testing & acceptance complete Planned: 2026-12-19 → 2026-12-19 Forecast: 2027-06-19 → 2027-06-19 Float: 102d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-09-29 0% Handover Planned: 2026-10-22 → 2027-06-30 Forecast: 2027-05-20 → 2027-09-29 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-09 0% Provisional acceptance Planned: 2026-10-22 → 2027-03-26 Forecast: 2027-05-20 → 2027-08-09 Float: 0d Drag to change its dates +136
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-09-29 0% Final acceptance Planned: 2027-01-27 → 2027-06-30 Forecast: 2027-07-10 → 2027-09-29 Float: 0d Drag to change its dates +91
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-09-29 0% Final handover Planned: 2027-06-30 → 2027-06-30 Forecast: 2027-09-29 → 2027-09-29 Float: 0d Drag to change its dates Final handover