SCA Backup Data Centre
Add to watchlistA Tier III backup data centre in Dammam that keeps Muqawil and the Authority’s systems running and recovers them after a disaster.
Budget (BAC)
Actual cost
79% of budget
Progress
Estimate at completion
SAR +14.6M
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-08-19 | 2025-10-18 | +60 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-01 | 2026-03-17 | +106 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-06 | 2026-10-26 | +173 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-18 | 2026-12-08 | +112 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-11-30 | 2027-01-09 | +40 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
72%Awaiting acceptance
8%Not handed in
20%Deliverable flow
Display options
| Project plan & baseline003-D1 | 5% | CRT-003-01 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Nayef H. Al-Buqami | 2025-06-28 | V1 | 3 of 3 |
| Monitoring & reporting003-D2 | 4% | CRT-003-02 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2025-08-19 | V1 | 3 of 3 |
| Business requirements003-D3 | 9% | CRT-003-03 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2025-10-10 | V1 | 3 of 3 |
| Solution design003-D4 | 9% | CRT-003-04 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Nayef H. Al-Buqami | 2025-12-01 | V1 | 3 of 3 |
| Release 1003-D5 | 15% | CRT-003-05 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Nayef H. Al-Buqami | 2026-01-22 | V1 | 3 of 3 |
| Release 2003-D6 | 15% | CRT-003-06 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Nayef H. Al-Buqami | 2026-03-15 | V1 | 3 of 3 |
| Integrations003-D7 | 15% | CRT-003-07 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2026-05-06 | V1 | 3 of 3 |
| System testing003-D8 | 8% | — | Under review | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Nayef H. Al-Buqami | 2026-06-27 | V1 | 1 of 3 |
| User acceptance testing003-D9 | 8% | — | Draft | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2026-08-18 | V0 | 0 of 3 |
| Training & change003-D10 | 6% | — | Draft | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2026-10-09 | V0 | 0 of 3 |
| Go-live & handover003-D11 | 6% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Nayef H. Al-Buqami | 2026-11-30 | V0 | 0 of 3 |
| Total · 11 | 100% |