Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-003At risk4ExecutionWaterfall

SCA Backup Data Centre

Add to watchlist

A Tier III backup data centre in Dammam that keeps Muqawil and the Authority’s systems running and recovers them after a disaster.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 148M

Actual cost

SAR 117.1M

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SAR 162.6M

SAR +14.6M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work143.6M⁦16⁩ elements
Unallocated contingency4.4MSAR 7.4M
Budget at completion148MPRJ-2026-003
Weighted progress⁦72%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project643⁦2025-04-06⁩⁦2027-01-09⁩⁦72%⁩143.56117.10—
1
Phase195⁦2025-04-06⁩⁦2025-10-18⁩⁦100%⁩11.4813.01—
1.1
WBS element120⁦2025-04-06⁩⁦2025-08-04⁩⁦100%⁩5.746.510 / 1
1.2
WBS element120⁦2025-06-20⁩⁦2025-10-18⁩⁦100%⁩5.746.511 / 2
2
Phase195⁦2025-09-03⁩⁦2026-03-17⁩⁦100%⁩24.4127.65—
2.1
WBS element120⁦2025-09-03⁩⁦2026-01-01⁩⁦100%⁩12.2013.821 / 1
2.2
WBS element120⁦2025-11-17⁩⁦2026-03-17⁩⁦100%⁩12.2013.821 / 2
3
Phase268⁦2026-01-31⁩⁦2026-10-26⁩⁦100%⁩57.4265.05—
3.1
WBS element120⁦2026-01-31⁩⁦2026-05-31⁩⁦100%⁩19.1421.681 / 1
3.2
WBS element120⁦2026-04-16⁩⁦2026-08-14⁩⁦100%⁩19.1421.691 / 1
3.3
WBS element118⁦2026-06-30⁩⁦2026-10-26⁩⁦100%⁩19.1421.691 / 2
4
Phase247⁦2026-04-05⁩⁦2026-12-08⁩⁦35%⁩28.7111.38—
4.1
WBS element231⁦2026-04-05⁩⁦2026-11-22⁩⁦70%⁩14.3611.381 / 1
4.2
WBS element25⁦2026-11-13⁩⁦2026-12-08⁩⁦0%⁩14.36—1 / 2
5
Phase41⁦2026-11-29⁩⁦2027-01-09⁩⁦0%⁩21.53——
5.1
WBS element25⁦2026-11-29⁩⁦2026-12-24⁩⁦0%⁩10.77—1 / 1
5.2
WBS element25⁦2026-12-15⁩⁦2027-01-09⁩⁦0%⁩10.77—1 / 1
Total⁦72%⁩143.56117.10
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close