Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦2⁩ — August 2024

HR self-service implementation

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
2
Date
⁦2024-09-02⁩
Hijri
29 Safar 1446 AH
Reference
PAY-2024-012-02

Interim payment certificate no. (⁦2⁩)

For the work of August 2024

Contract number
SCA/2024/012
Etimad reference
2401850160
Contract
HR self-service implementation
Contractor
Integrated Business Systems Co.
Contractor VAT number
310104366820003
Project
HR Self-Service
Contract period
⁦2024-06-02⁩ — ⁦2025-09-30⁩
Original contract value
8,800,000
Current contract value
8,800,000
Linked milestone
Design approved · MS-G1 Project plan approved

Certificate summary (SAR)

1Total value of work completed to date1,060,000
2Less: previous certificates(400,000)
3Value of work in this certificate660,000
4Less: retention (⁦5%⁩)(33,000)
5Less: advance payment recovery (⁦10%⁩)(66,000)
6Less: delay and breach penalties0
7Total deductions(99,000)
8Net before VAT561,000
9Add: value added tax (15%)84,150
10Net amount payable to the contractor645,150

Amount in words: Six hundred forty-five thousand one hundred fifty Saudi riyals only

Retention held up to this certificate: SAR 53K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design1,320,00093,000140,000233,000⁦18%⁩
Licences & platform1,760,000107,000169,000276,000⁦16%⁩
Build & configuration2,640,000118,000200,000318,000⁦12%⁩
Systems integration1,320,00046,00081,000127,000⁦10%⁩
Testing & acceptance880,00022,00042,00064,000⁦7%⁩
Training & run880,00014,00028,00042,000⁦5%⁩
Total8,800,000400,000660,0001,060,000⁦12%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Mona F. Al-Harbi

Al-Harbi⁦2024-09-02⁩

Supervising engineer

Hussam T. Al-Qurashi

Al-Qurashi⁦2024-09-04⁩

Project manager

Dana S. Al-Saleh

Al-Saleh⁦2024-09-07⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-09-10⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2024-09-13⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-09-02⁩

    Mona F. Al-Harbi

  2. Engineer verifies quantities⁦2024-09-04⁩

    Hussam T. Al-Qurashi · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2024-09-07⁩

    Dana S. Al-Saleh · Director, Enterprise Systems & Integration

    Took 3 days

  4. Payment order prepared⁦2024-09-10⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-09-13⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneDesign approvedDone · ⁦2024-10-01⁩
  2. Project milestoneMS-G1Project plan approvedMilestone approved ⁦2024-08-26⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHussam T. Al-Qurashi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentDana S. Al-Saleh → Munirah A. Al-Khalidi

Certificate history

13 September 2024

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2024-09-13 13:00

10 September 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-09-10 13:00

7 September 2024

  1. Approval: Dana S. Al-Saleh signed “Project manager certifies”

    2024-09-07 13:00

4 September 2024

  1. Approval: Hussam T. Al-Qurashi signed “Engineer verifies quantities”

    2024-09-04 13:00

2 September 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-09-02 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close