Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2026-03-11
- Hijri
- 22 Ramadan 1447 AH
- Reference
- PAY-2025-005-06
Interim payment certificate no. (6)
For the work of February 2026
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 28,600,000 |
| 2 | Less: previous certificates | (23,350,000) |
| 3 | Value of work in this certificate | 5,250,000 |
| 4 | Less: retention (10%) | (525,000) |
| 5 | Less: advance payment recovery (10%) | (525,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,050,000) |
| 8 | Net before VAT | 4,200,000 |
| 9 | Add: value added tax (15%) | 630,000 |
| 10 | Net amount payable to the contractor | 4,830,000 |
Amount in words: Four million eight hundred thirty thousand Saudi riyals only
Retention held up to this certificate: SAR 2.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 3,865,000 | 753,000 | 4,618,000 | 81% |
| Earthworks & foundations | 14,580,000 | 5,993,000 | 1,214,000 | 7,207,000 | 49% |
| Concrete & structural works | 25,110,000 | 7,952,000 | 1,801,000 | 9,753,000 | 39% |
| Mechanical, electrical & plumbing | 19,440,000 | 3,814,000 | 991,000 | 4,805,000 | 25% |
| Finishes & external works | 12,150,000 | 1,507,000 | 424,000 | 1,931,000 | 16% |
| Testing & commissioning | 4,050,000 | 219,000 | 67,000 | 286,000 | 7% |
| Total | 81,000,000 | 23,350,000 | 5,250,000 | 28,600,000 | 35% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani