Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 10
- Date
- 2026-10-06
- Hijri
- 25 Rabiʻ II 1448 AH
- Reference
- PAY-2026-014
Interim payment certificate no. (10)
For the work of September 2026
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 44,300,000 |
| 2 | Less: previous certificates | (40,100,000) |
| 3 | Value of work in this certificate | 4,200,000 |
| 4 | Less: retention (10%) | (420,000) |
| 5 | Less: advance payment recovery (10%) | (420,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (840,000) |
| 8 | Net before VAT | 3,360,000 |
| 9 | Add: value added tax (15%) | 504,000 |
| 10 | Net amount payable to the contractor | 3,864,000 |
Amount in words: Three million eight hundred sixty-four thousand Saudi riyals only
Retention held up to this certificate: SAR 4.4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 5,246,000 | 424,000 | 5,670,000 | 100% |
| Earthworks & foundations | 14,580,000 | 11,638,000 | 1,011,000 | 12,649,000 | 87% |
| Concrete & structural works | 25,110,000 | 13,661,000 | 1,445,000 | 15,106,000 | 60% |
| Mechanical, electrical & plumbing | 19,440,000 | 6,574,000 | 868,000 | 7,442,000 | 38% |
| Finishes & external works | 12,150,000 | 2,602,000 | 388,000 | 2,990,000 | 25% |
| Testing & commissioning | 4,050,000 | 379,000 | 64,000 | 443,000 | 11% |
| Total | 81,000,000 | 40,100,000 | 4,200,000 | 44,300,000 | 55% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani