Certificate ⁦10⁩ — September 2026

Solar PV supply & installation — SCA buildings & centres

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
10
Date
⁦2026-10-06⁩
Hijri
25 Rabiʻ II 1448 AH
Reference
PAY-2026-014

Interim payment certificate no. (⁦10⁩)

For the work of September 2026

Contract number
SCA/2025/005
Etimad reference
2503460459
Contract
Solar PV supply & installation — SCA buildings & centres
Contractor
Sustainable Energy Contracting Est.
Contractor VAT number
335500417280003
Project
Solar Power for SCA Buildings & Centres
Contract period
⁦2025-04-06⁩ — ⁦2027-04-30⁩
Original contract value
81,000,000
Current contract value
81,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date44,300,000
2Less: previous certificates(40,100,000)
3Value of work in this certificate4,200,000
4Less: retention (⁦10%⁩)(420,000)
5Less: advance payment recovery (⁦10%⁩)(420,000)
6Less: delay and breach penalties0
7Total deductions(840,000)
8Net before VAT3,360,000
9Add: value added tax (15%)504,000
10Net amount payable to the contractor3,864,000

Amount in words: Three million eight hundred sixty-four thousand Saudi riyals only

Retention held up to this certificate: SAR 4.4M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation5,670,0005,246,000424,0005,670,000⁦100%⁩
Earthworks & foundations14,580,00011,638,0001,011,00012,649,000⁦87%⁩
Concrete & structural works25,110,00013,661,0001,445,00015,106,000⁦60%⁩
Mechanical, electrical & plumbing19,440,0006,574,000868,0007,442,000⁦38%⁩
Finishes & external works12,150,0002,602,000388,0002,990,000⁦25%⁩
Testing & commissioning4,050,000379,00064,000443,000⁦11%⁩
Total81,000,00040,100,0004,200,00044,300,000⁦55%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Abdulelah M. Al-Anazi

Al-Anazi⁦2026-10-06⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-10-08⁩

Project manager

Eng. Mishari K. Al-Otaibi

Al-Otaibi⁦2026-10-11⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-10-14⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-10-17⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-10-06⁩

    Eng. Abdulelah M. Al-Anazi

  2. Engineer verifies quantities⁦2026-10-08⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-10-11⁩

    Eng. Mishari K. Al-Otaibi · Director, Sustainability & Energy Efficiency

    Took 3 days

  4. Payment order prepared⁦2026-10-14⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-10-17⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedIn progress · ⁦2026-11-15⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Mishari K. Al-Otaibi → Dr. Abdullah S. Al-Qahtani

Certificate history

17 October 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-10-17 13:00

14 October 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-10-14 13:00

11 October 2026

  1. Approval: Eng. Mishari K. Al-Otaibi signed “Project manager certifies”

    2026-10-11 13:00

8 October 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-10-08 13:00

6 October 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-10-06 09:00