Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 8
- Date
- 2026-07-07
- Hijri
- 22 Muharram 1448 AH
- Reference
- PAY-2025-005-08
Interim payment certificate no. (8)
For the work of June 2026
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 37,810,000 |
| 2 | Less: previous certificates | (34,110,000) |
| 3 | Value of work in this certificate | 3,700,000 |
| 4 | Less: retention (10%) | (370,000) |
| 5 | Less: advance payment recovery (10%) | (370,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (740,000) |
| 8 | Net before VAT | 2,960,000 |
| 9 | Add: value added tax (15%) | 444,000 |
| 10 | Net amount payable to the contractor | 3,404,000 |
Amount in words: Three million four hundred four thousand Saudi riyals only
Retention held up to this certificate: SAR 3.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 5,207,000 | 463,000 | 5,670,000 | 100% |
| Earthworks & foundations | 14,580,000 | 9,109,000 | 856,000 | 9,965,000 | 68% |
| Concrete & structural works | 25,110,000 | 11,621,000 | 1,272,000 | 12,893,000 | 51% |
| Mechanical, electrical & plumbing | 19,440,000 | 5,618,000 | 734,000 | 6,352,000 | 33% |
| Finishes & external works | 12,150,000 | 2,230,000 | 322,000 | 2,552,000 | 21% |
| Testing & commissioning | 4,050,000 | 325,000 | 53,000 | 378,000 | 9% |
| Total | 81,000,000 | 34,110,000 | 3,700,000 | 37,810,000 | 47% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani