Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦8⁩ — June 2026

Solar PV supply & installation — SCA buildings & centres

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
8
Date
⁦2026-07-07⁩
Hijri
22 Muharram 1448 AH
Reference
PAY-2025-005-08

Interim payment certificate no. (⁦8⁩)

For the work of June 2026

Contract number
SCA/2025/005
Etimad reference
2503460459
Contract
Solar PV supply & installation — SCA buildings & centres
Contractor
Sustainable Energy Contracting Est.
Contractor VAT number
335500417280003
Project
Solar Power for SCA Buildings & Centres
Contract period
⁦2025-04-06⁩ — ⁦2027-04-30⁩
Original contract value
81,000,000
Current contract value
81,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date37,810,000
2Less: previous certificates(34,110,000)
3Value of work in this certificate3,700,000
4Less: retention (⁦10%⁩)(370,000)
5Less: advance payment recovery (⁦10%⁩)(370,000)
6Less: delay and breach penalties0
7Total deductions(740,000)
8Net before VAT2,960,000
9Add: value added tax (15%)444,000
10Net amount payable to the contractor3,404,000

Amount in words: Three million four hundred four thousand Saudi riyals only

Retention held up to this certificate: SAR 3.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation5,670,0005,207,000463,0005,670,000⁦100%⁩
Earthworks & foundations14,580,0009,109,000856,0009,965,000⁦68%⁩
Concrete & structural works25,110,00011,621,0001,272,00012,893,000⁦51%⁩
Mechanical, electrical & plumbing19,440,0005,618,000734,0006,352,000⁦33%⁩
Finishes & external works12,150,0002,230,000322,0002,552,000⁦21%⁩
Testing & commissioning4,050,000325,00053,000378,000⁦9%⁩
Total81,000,00034,110,0003,700,00037,810,000⁦47%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Abdulelah M. Al-Anazi

Al-Anazi⁦2026-07-07⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-07-09⁩

Project manager

Eng. Mishari K. Al-Otaibi

Al-Otaibi⁦2026-07-12⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-07-15⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-07-18⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-07⁩

    Eng. Abdulelah M. Al-Anazi

  2. Engineer verifies quantities⁦2026-07-09⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-07-12⁩

    Eng. Mishari K. Al-Otaibi · Director, Sustainability & Energy Efficiency

    Took 3 days

  4. Payment order prepared⁦2026-07-15⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-18⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedIn progress · ⁦2026-11-15⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Mishari K. Al-Otaibi → Dr. Abdullah S. Al-Qahtani

Certificate history

18 July 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-07-18 13:00

15 July 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-07-15 13:00

12 July 2026

  1. Approval: Eng. Mishari K. Al-Otaibi signed “Project manager certifies”

    2026-07-12 13:00

9 July 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-07-09 13:00

7 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-07 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close