Interim payment certificate no. (9)
For the work of August 2026
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 40,100,000 |
| 2 | Less: previous certificates | (37,810,000) |
| 3 | Value of work in this certificate | 2,290,000 |
| 4 | Less: retention (10%) | (229,000) |
| 5 | Less: advance payment recovery (10%) | (229,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (458,000) |
| 8 | Net before VAT | 1,832,000 |
| 9 | Add: value added tax (15%) | 274,800 |
| 10 | Net amount payable to the contractor | 2,106,800 |
Amount in words: Two million one hundred six thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 5,405,000 | 265,000 | 5,670,000 | 100% |
| Earthworks & foundations | 14,580,000 | 10,371,000 | 540,000 | 10,911,000 | 75% |
| Concrete & structural works | 25,110,000 | 12,886,000 | 788,000 | 13,674,000 | 54% |
| Mechanical, electrical & plumbing | 19,440,000 | 6,276,000 | 461,000 | 6,737,000 | 35% |
| Finishes & external works | 12,150,000 | 2,504,000 | 203,000 | 2,707,000 | 22% |
| Testing & commissioning | 4,050,000 | 368,000 | 33,000 | 401,000 | 10% |
| Total | 81,000,000 | 37,810,000 | 2,290,000 | 40,100,000 | 50% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani