Certificate ⁦5⁩ — December 2025

Solar PV supply & installation — SCA buildings & centres

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
5
Date
⁦2026-01-12⁩
Hijri
23 Rajab 1447 AH
Reference
PAY-2025-005-05

Interim payment certificate no. (⁦5⁩)

For the work of December 2025

Contract number
SCA/2025/005
Etimad reference
2503460459
Contract
Solar PV supply & installation — SCA buildings & centres
Contractor
Sustainable Energy Contracting Est.
Contractor VAT number
335500417280003
Project
Solar Power for SCA Buildings & Centres
Contract period
⁦2025-04-06⁩ — ⁦2027-04-30⁩
Original contract value
81,000,000
Current contract value
81,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date23,350,000
2Less: previous certificates(17,120,000)
3Value of work in this certificate6,230,000
4Less: retention (⁦10%⁩)(623,000)
5Less: advance payment recovery (⁦10%⁩)(623,000)
6Less: delay and breach penalties0
7Total deductions(1,246,000)
8Net before VAT4,984,000
9Add: value added tax (15%)747,600
10Net amount payable to the contractor5,731,600

Amount in words: Five million seven hundred thirty-one thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 2.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation5,670,0002,851,000920,0003,771,000⁦67%⁩
Earthworks & foundations14,580,0004,413,0001,471,0005,884,000⁦40%⁩
Concrete & structural works25,110,0005,828,0002,134,0007,962,000⁦32%⁩
Mechanical, electrical & plumbing19,440,0002,777,0001,146,0003,923,000⁦20%⁩
Finishes & external works12,150,0001,092,000484,0001,576,000⁦13%⁩
Testing & commissioning4,050,000159,00075,000234,000⁦6%⁩
Total81,000,00017,120,0006,230,00023,350,000⁦29%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Abdulelah M. Al-Anazi

Al-Anazi⁦2026-01-12⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-01-14⁩

Project manager

Eng. Mishari K. Al-Otaibi

Al-Otaibi⁦2026-01-17⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-01-20⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-01-23⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-12⁩

    Eng. Abdulelah M. Al-Anazi

  2. Engineer verifies quantities⁦2026-01-14⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-01-17⁩

    Eng. Mishari K. Al-Otaibi · Director, Sustainability & Energy Efficiency

    Took 3 days

  4. Payment order prepared⁦2026-01-20⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-23⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-05-26⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-10-26⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Mishari K. Al-Otaibi → Dr. Abdullah S. Al-Qahtani

Certificate history

23 January 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-01-23 13:00

20 January 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-01-20 13:00

17 January 2026

  1. Approval: Eng. Mishari K. Al-Otaibi signed “Project manager certifies”

    2026-01-17 13:00

14 January 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-01-14 13:00

12 January 2026