Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2026-01-12
- Hijri
- 23 Rajab 1447 AH
- Reference
- PAY-2025-005-05
Interim payment certificate no. (5)
For the work of December 2025
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 23,350,000 |
| 2 | Less: previous certificates | (17,120,000) |
| 3 | Value of work in this certificate | 6,230,000 |
| 4 | Less: retention (10%) | (623,000) |
| 5 | Less: advance payment recovery (10%) | (623,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,246,000) |
| 8 | Net before VAT | 4,984,000 |
| 9 | Add: value added tax (15%) | 747,600 |
| 10 | Net amount payable to the contractor | 5,731,600 |
Amount in words: Five million seven hundred thirty-one thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 2.3M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 2,851,000 | 920,000 | 3,771,000 | 67% |
| Earthworks & foundations | 14,580,000 | 4,413,000 | 1,471,000 | 5,884,000 | 40% |
| Concrete & structural works | 25,110,000 | 5,828,000 | 2,134,000 | 7,962,000 | 32% |
| Mechanical, electrical & plumbing | 19,440,000 | 2,777,000 | 1,146,000 | 3,923,000 | 20% |
| Finishes & external works | 12,150,000 | 1,092,000 | 484,000 | 1,576,000 | 13% |
| Testing & commissioning | 4,050,000 | 159,000 | 75,000 | 234,000 | 6% |
| Total | 81,000,000 | 17,120,000 | 6,230,000 | 23,350,000 | 29% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani