Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 4
- Date
- 2025-11-14
- Hijri
- 23 Jumada I 1447 AH
- Reference
- PAY-2025-005-04
Interim payment certificate no. (4)
For the work of October 2025
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 17,120,000 |
| 2 | Less: previous certificates | (10,950,000) |
| 3 | Value of work in this certificate | 6,170,000 |
| 4 | Less: retention (10%) | (617,000) |
| 5 | Less: advance payment recovery (10%) | (617,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,234,000) |
| 8 | Net before VAT | 4,936,000 |
| 9 | Add: value added tax (15%) | 740,400 |
| 10 | Net amount payable to the contractor | 5,676,400 |
Amount in words: Five million six hundred seventy-six thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 1.7M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 1,827,000 | 938,000 | 2,765,000 | 49% |
| Earthworks & foundations | 14,580,000 | 2,827,000 | 1,487,000 | 4,314,000 | 30% |
| Concrete & structural works | 25,110,000 | 3,727,000 | 2,111,000 | 5,838,000 | 23% |
| Mechanical, electrical & plumbing | 19,440,000 | 1,772,000 | 1,104,000 | 2,876,000 | 15% |
| Finishes & external works | 12,150,000 | 696,000 | 460,000 | 1,156,000 | 10% |
| Testing & commissioning | 4,050,000 | 101,000 | 70,000 | 171,000 | 4% |
| Total | 81,000,000 | 10,950,000 | 6,170,000 | 17,120,000 | 21% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani