Interim payment certificate no. (7)
For the work of April 2026
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 34,110,000 |
| 2 | Less: previous certificates | (28,600,000) |
| 3 | Value of work in this certificate | 5,510,000 |
| 4 | Less: retention (10%) | (551,000) |
| 5 | Less: advance payment recovery (10%) | (551,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,102,000) |
| 8 | Net before VAT | 4,408,000 |
| 9 | Add: value added tax (15%) | 661,200 |
| 10 | Net amount payable to the contractor | 5,069,200 |
Amount in words: Five million sixty-nine thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 3.4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 4,745,000 | 764,000 | 5,509,000 | 97% |
| Earthworks & foundations | 14,580,000 | 7,352,000 | 1,244,000 | 8,596,000 | 59% |
| Concrete & structural works | 25,110,000 | 9,739,000 | 1,893,000 | 11,632,000 | 46% |
| Mechanical, electrical & plumbing | 19,440,000 | 4,659,000 | 1,071,000 | 5,730,000 | 29% |
| Finishes & external works | 12,150,000 | 1,837,000 | 465,000 | 2,302,000 | 19% |
| Testing & commissioning | 4,050,000 | 268,000 | 73,000 | 341,000 | 8% |
| Total | 81,000,000 | 28,600,000 | 5,510,000 | 34,110,000 | 42% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani