SCA/2025/005
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
55% of the current value paid
Paid
44.3Mof a current value of SAR 81M
Value of each certificate
The last 10 — gross and net
Approved: 10
Count: 10 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 10September 2026 | 2026-10-06 | 4.2M | 420K | 420K | 504K | 3.9M | Approved | |
| Certificate 9August 2026 | 2026-09-04 | 2.3M | 229K | 229K | 274.8K | 2.1M | Approved | |
| Certificate 8June 2026 | 2026-07-07 | 3.7M | 370K | 370K | 444K | 3.4M | Approved | |
| Certificate 7April 2026 | 2026-05-09 | 5.5M | 551K | 551K | 661.2K | 5.1M | Approved | |
| Certificate 6February 2026 | 2026-03-11 | 5.3M | 525K | 525K | 630K | 4.8M | Approved | |
| Certificate 5December 2025 | 2026-01-12 | 6.2M | 623K | 623K | 747.6K | 5.7M | Approved | |
| Certificate 4October 2025 | 2025-11-14 | 6.2M | 617K | 617K | 740.4K | 5.7M | Approved | |
| Certificate 3August 2025 | 2025-09-16 | 4.5M | 451K | 451K | 541.2K | 4.1M | Approved | |
| Certificate 2June 2025 | 2025-07-19 | 4.1M | 408K | 408K | 489.6K | 3.8M | Approved | |
| Certificate 1May 2025 | 2025-05-21 | 2.4M | 236K | 236K | 283.2K | 2.2M | Approved |