Interim payment certificate no. (1)
For the work of May 2025
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- Site handover & mobilisation · MS-G1 Project plan approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 2,360,000 |
| 2 | Less: previous certificates | 0 |
| 3 | Value of work in this certificate | 2,360,000 |
| 4 | Less: retention (10%) | (236,000) |
| 5 | Less: advance payment recovery (10%) | (236,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (472,000) |
| 8 | Net before VAT | 1,888,000 |
| 9 | Add: value added tax (15%) | 283,200 |
| 10 | Net amount payable to the contractor | 2,171,200 |
Amount in words: Two million one hundred seventy-one thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 236K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 0 | 381,000 | 381,000 | 7% |
| Earthworks & foundations | 14,580,000 | 0 | 595,000 | 595,000 | 4% |
| Concrete & structural works | 25,110,000 | 0 | 805,000 | 805,000 | 3% |
| Mechanical, electrical & plumbing | 19,440,000 | 0 | 396,000 | 396,000 | 2% |
| Finishes & external works | 12,150,000 | 0 | 159,000 | 159,000 | 1% |
| Testing & commissioning | 4,050,000 | 0 | 24,000 | 24,000 | 1% |
| Total | 81,000,000 | 0 | 2,360,000 | 2,360,000 | 3% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani