Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦2⁩ — June 2025

Solar PV supply & installation — SCA buildings & centres

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
2
Date
⁦2025-07-19⁩
Hijri
24 Muharram 1447 AH
Reference
PAY-2025-005-02

Interim payment certificate no. (⁦2⁩)

For the work of June 2025

Contract number
SCA/2025/005
Etimad reference
2503460459
Contract
Solar PV supply & installation — SCA buildings & centres
Contractor
Sustainable Energy Contracting Est.
Contractor VAT number
335500417280003
Project
Solar Power for SCA Buildings & Centres
Contract period
⁦2025-04-06⁩ — ⁦2027-04-30⁩
Original contract value
81,000,000
Current contract value
81,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date6,440,000
2Less: previous certificates(2,360,000)
3Value of work in this certificate4,080,000
4Less: retention (⁦10%⁩)(408,000)
5Less: advance payment recovery (⁦10%⁩)(408,000)
6Less: delay and breach penalties0
7Total deductions(816,000)
8Net before VAT3,264,000
9Add: value added tax (15%)489,600
10Net amount payable to the contractor3,753,600

Amount in words: Three million seven hundred fifty-three thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 644K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation5,670,000394,000646,0001,040,000⁦18%⁩
Earthworks & foundations14,580,000610,0001,013,0001,623,000⁦11%⁩
Concrete & structural works25,110,000803,0001,393,0002,196,000⁦9%⁩
Mechanical, electrical & plumbing19,440,000381,000701,0001,082,000⁦6%⁩
Finishes & external works12,150,000150,000285,000435,000⁦4%⁩
Testing & commissioning4,050,00022,00042,00064,000⁦2%⁩
Total81,000,0002,360,0004,080,0006,440,000⁦8%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Abdulelah M. Al-Anazi

Al-Anazi⁦2025-07-19⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-07-21⁩

Project manager

Eng. Mishari K. Al-Otaibi

Al-Otaibi⁦2025-07-24⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-07-27⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-07-30⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-07-19⁩

    Eng. Abdulelah M. Al-Anazi

  2. Engineer verifies quantities⁦2025-07-21⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-07-24⁩

    Eng. Mishari K. Al-Otaibi · Director, Sustainability & Energy Efficiency

    Took 3 days

  4. Payment order prepared⁦2025-07-27⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-07-30⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-11-03⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-03-03⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Mishari K. Al-Otaibi → Dr. Abdullah S. Al-Qahtani

Certificate history

30 July 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-07-30 13:00

27 July 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-07-27 13:00

24 July 2025

  1. Approval: Eng. Mishari K. Al-Otaibi signed “Project manager certifies”

    2025-07-24 13:00

21 July 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-07-21 13:00

19 July 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-07-19 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close