Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-09-16
- Hijri
- 24 Rabiʻ I 1447 AH
- Reference
- PAY-2025-005-03
Interim payment certificate no. (3)
For the work of August 2025
- Contract number
- SCA/2025/005
- Etimad reference
- 2503460459
- Contract
- Solar PV supply & installation — SCA buildings & centres
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for SCA Buildings & Centres
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 81,000,000
- Current contract value
- 81,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 10,950,000 |
| 2 | Less: previous certificates | (6,440,000) |
| 3 | Value of work in this certificate | 4,510,000 |
| 4 | Less: retention (10%) | (451,000) |
| 5 | Less: advance payment recovery (10%) | (451,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (902,000) |
| 8 | Net before VAT | 3,608,000 |
| 9 | Add: value added tax (15%) | 541,200 |
| 10 | Net amount payable to the contractor | 4,149,200 |
Amount in words: Four million one hundred forty-nine thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 1.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 5,670,000 | 1,066,000 | 702,000 | 1,768,000 | 31% |
| Earthworks & foundations | 14,580,000 | 1,652,000 | 1,107,000 | 2,759,000 | 19% |
| Concrete & structural works | 25,110,000 | 2,193,000 | 1,541,000 | 3,734,000 | 15% |
| Mechanical, electrical & plumbing | 19,440,000 | 1,052,000 | 788,000 | 1,840,000 | 9% |
| Finishes & external works | 12,150,000 | 416,000 | 323,000 | 739,000 | 6% |
| Testing & commissioning | 4,050,000 | 61,000 | 49,000 | 110,000 | 3% |
| Total | 81,000,000 | 6,440,000 | 4,510,000 | 10,950,000 | 14% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani