Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦8⁩ — February 2026

Correspondence & document management system — supply & implementation

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
8
Date
⁦2026-03-01⁩
Hijri
12 Ramadan 1447 AH
Reference
PAY-2025-019-08

Interim payment certificate no. (⁦8⁩)

For the work of February 2026

Contract number
SCA/2025/019
Etimad reference
2504440641
Contract
Correspondence & document management system — supply & implementation
Contractor
Integrated Business Systems Co.
Contractor VAT number
310104366820003
Project
Correspondence & Document Management System (DMS)
Contract period
⁦2025-02-16⁩ — ⁦2026-09-30⁩
Original contract value
11,600,000
Current contract value
11,600,000
Linked milestone
Integration & UAT · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date6,850,000
2Less: previous certificates(5,820,000)
3Value of work in this certificate1,030,000
4Less: retention (⁦10%⁩)(103,000)
5Less: advance payment recovery (⁦10%⁩)(103,000)
6Less: delay and breach penalties0
7Total deductions(206,000)
8Net before VAT824,000
9Add: value added tax (15%)123,600
10Net amount payable to the contractor947,600

Amount in words: Nine hundred forty-seven thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 685K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design1,740,0001,335,000172,0001,507,000⁦87%⁩
Licences & platform2,320,0001,544,000237,0001,781,000⁦77%⁩
Build & configuration3,480,0001,724,000331,0002,055,000⁦59%⁩
Systems integration1,740,000674,000148,000822,000⁦47%⁩
Testing & acceptance1,160,000329,00082,000411,000⁦35%⁩
Training & run1,160,000214,00060,000274,000⁦24%⁩
Total11,600,0005,820,0001,030,0006,850,000⁦59%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Mona F. Al-Harbi

Al-Harbi⁦2026-03-01⁩

Supervising engineer

Hussam T. Al-Qurashi

Al-Qurashi⁦2026-03-03⁩

Project manager

Dana S. Al-Saleh

Al-Saleh⁦2026-03-06⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-03-09⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2026-03-12⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-01⁩

    Mona F. Al-Harbi

  2. Engineer verifies quantities⁦2026-03-03⁩

    Hussam T. Al-Qurashi · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2026-03-06⁩

    Dana S. Al-Saleh · Director, Enterprise Systems & Integration

    Took 3 days

  4. Payment order prepared⁦2026-03-09⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-12⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneIntegration & UATDone · ⁦2026-04-06⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-04-28⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHussam T. Al-Qurashi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentDana S. Al-Saleh → Munirah A. Al-Khalidi

Certificate history

12 March 2026

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2026-03-12 13:00

9 March 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-03-09 13:00

6 March 2026

  1. Approval: Dana S. Al-Saleh signed “Project manager certifies”

    2026-03-06 13:00

3 March 2026

  1. Approval: Hussam T. Al-Qurashi signed “Engineer verifies quantities”

    2026-03-03 13:00

1 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-01 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close