SCA/2025/019
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
90% of the current value paid
Paid
10.4Mof a current value of SAR 11.6M
Value of each certificate
The last 13 — gross and net
Approved: 13
Count: 13 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 13October 2026 | 2026-10-25 | 380K | 38K | 38K | 45.6K | 349.6K | Approved | |
| Certificate 12August 2026 | 2026-09-07 | 580K | 58K | 58K | 69.6K | 533.6K | Approved | |
| Certificate 11July 2026 | 2026-07-22 | 690K | 69K | 69K | 82.8K | 634.8K | Approved | |
| Certificate 10May 2026 | 2026-06-04 | 980K | 98K | 98K | 117.6K | 901.6K | Approved | |
| Certificate 9March 2026 | 2026-04-18 | 960K | 96K | 96K | 115.2K | 883.2K | Approved | |
| Certificate 8February 2026 | 2026-03-01 | 1M | 103K | 103K | 123.6K | 947.6K | Approved | |
| Certificate 7December 2025 | 2026-01-13 | 1.2M | 121K | 121K | 145.2K | 1.1M | Approved | |
| Certificate 6November 2025 | 2025-11-26 | 970K | 97K | 97K | 116.4K | 892.4K | Approved | |
| Certificate 5September 2025 | 2025-10-09 | 1M | 103K | 103K | 123.6K | 947.6K | Approved | |
| Certificate 4August 2025 | 2025-08-23 | 950K | 95K | 95K | 114K | 874K | Approved | |
| Certificate 3June 2025 | 2025-07-06 | 680K | 68K | 68K | 81.6K | 625.6K | Approved | |
| Certificate 2April 2025 | 2025-05-20 | 600K | 60K | 60K | 72K | 552K | Approved | |
| Certificate 1March 2025 | 2025-04-02 | 380K | 38K | 38K | 45.6K | 349.6K | Approved |