Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 7
- Date
- 2026-04-08
- Hijri
- 20 Shawwal 1447 AH
- Reference
- PAY-2025-023-07
Interim payment certificate no. (7)
For the work of March 2026
- Contract number
- SCA/2025/023
- Etimad reference
- 2504720693
- Contract
- Hail vocational qualification centre — construction
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Hail Vocational Qualification Centre
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 118,000,000
- Current contract value
- 118,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 49,690,000 |
| 2 | Less: previous certificates | (40,720,000) |
| 3 | Value of work in this certificate | 8,970,000 |
| 4 | Less: retention (10%) | (897,000) |
| 5 | Less: advance payment recovery (10%) | (897,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,794,000) |
| 8 | Net before VAT | 7,176,000 |
| 9 | Add: value added tax (15%) | 1,076,400 |
| 10 | Net amount payable to the contractor | 8,252,400 |
Amount in words: Eight million two hundred fifty-two thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 8,260,000 | 6,782,000 | 1,243,000 | 8,025,000 | 97% |
| Earthworks & foundations | 21,240,000 | 10,498,000 | 2,024,000 | 12,522,000 | 59% |
| Concrete & structural works | 36,580,000 | 13,862,000 | 3,082,000 | 16,944,000 | 46% |
| Mechanical, electrical & plumbing | 28,320,000 | 6,605,000 | 1,743,000 | 8,348,000 | 29% |
| Finishes & external works | 17,700,000 | 2,597,000 | 757,000 | 3,354,000 | 19% |
| Testing & commissioning | 5,900,000 | 376,000 | 121,000 | 497,000 | 8% |
| Total | 118,000,000 | 40,720,000 | 8,970,000 | 49,690,000 | 42% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani