Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦6⁩ — January 2026

Hail vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
6
Date
⁦2026-02-13⁩
Hijri
25 Shaʻban 1447 AH
Reference
PAY-2025-023-06

Interim payment certificate no. (⁦6⁩)

For the work of January 2026

Contract number
SCA/2025/023
Etimad reference
2504720693
Contract
Hail vocational qualification centre — construction
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
Hail Vocational Qualification Centre
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
118,000,000
Current contract value
118,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date40,720,000
2Less: previous certificates(32,800,000)
3Value of work in this certificate7,920,000
4Less: retention (⁦10%⁩)(792,000)
5Less: advance payment recovery (⁦10%⁩)(792,000)
6Less: delay and breach penalties0
7Total deductions(1,584,000)
8Net before VAT6,336,000
9Add: value added tax (15%)950,400
10Net amount payable to the contractor7,286,400

Amount in words: Seven million two hundred eighty-six thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 4.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation8,260,0005,435,0001,141,0006,576,000⁦80%⁩
Earthworks & foundations21,240,0008,424,0001,837,00010,261,000⁦48%⁩
Concrete & structural works36,580,00011,170,0002,716,00013,886,000⁦38%⁩
Mechanical, electrical & plumbing28,320,0005,351,0001,490,0006,841,000⁦24%⁩
Finishes & external works17,700,0002,112,000637,0002,749,000⁦16%⁩
Testing & commissioning5,900,000308,00099,000407,000⁦7%⁩
Total118,000,00032,800,0007,920,00040,720,000⁦35%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2026-02-13⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-15⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2026-02-18⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-02-21⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-02-24⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-13⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2026-02-15⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-02-18⁩

    Eng. Fahad T. Al-Sulami · Director, Regional Qualification Centres

    Took 3 days

  4. Payment order prepared⁦2026-02-21⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-02-24⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-04-22⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

24 February 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-02-24 13:00

21 February 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-02-21 13:00

18 February 2026

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2026-02-18 13:00

15 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-02-15 13:00

13 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-13 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close