Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2025-12-22
- Hijri
- 2 Rajab 1447 AH
- Reference
- PAY-2025-023-05
Interim payment certificate no. (5)
For the work of December 2025
- Contract number
- SCA/2025/023
- Etimad reference
- 2504720693
- Contract
- Hail vocational qualification centre — construction
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Hail Vocational Qualification Centre
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 118,000,000
- Current contract value
- 118,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 32,800,000 |
| 2 | Less: previous certificates | (23,810,000) |
| 3 | Value of work in this certificate | 8,990,000 |
| 4 | Less: retention (10%) | (899,000) |
| 5 | Less: advance payment recovery (10%) | (899,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,798,000) |
| 8 | Net before VAT | 7,192,000 |
| 9 | Add: value added tax (15%) | 1,078,800 |
| 10 | Net amount payable to the contractor | 8,270,800 |
Amount in words: Eight million two hundred seventy thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 3.3M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 8,260,000 | 3,964,000 | 1,333,000 | 5,297,000 | 64% |
| Earthworks & foundations | 21,240,000 | 6,137,000 | 2,129,000 | 8,266,000 | 39% |
| Concrete & structural works | 36,580,000 | 8,106,000 | 3,079,000 | 11,185,000 | 31% |
| Mechanical, electrical & plumbing | 28,320,000 | 3,863,000 | 1,647,000 | 5,510,000 | 19% |
| Finishes & external works | 17,700,000 | 1,519,000 | 695,000 | 2,214,000 | 13% |
| Testing & commissioning | 5,900,000 | 221,000 | 107,000 | 328,000 | 6% |
| Total | 118,000,000 | 23,810,000 | 8,990,000 | 32,800,000 | 28% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani