Certificate ⁦8⁩ — May 2026

Hail vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
8
Date
⁦2026-06-01⁩
Hijri
15 Dhuʻl-Hijjah 1447 AH
Reference
PAY-2025-023-08

Interim payment certificate no. (⁦8⁩)

For the work of May 2026

Contract number
SCA/2025/023
Etimad reference
2504720693
Contract
Hail vocational qualification centre — construction
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
Hail Vocational Qualification Centre
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
118,000,000
Current contract value
118,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date56,360,000
2Less: previous certificates(49,690,000)
3Value of work in this certificate6,670,000
4Less: retention (⁦10%⁩)(667,000)
5Less: advance payment recovery (⁦10%⁩)(667,000)
6Less: delay and breach penalties0
7Total deductions(1,334,000)
8Net before VAT5,336,000
9Add: value added tax (15%)800,400
10Net amount payable to the contractor6,136,400

Amount in words: Six million one hundred thirty-six thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 5.6M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation8,260,0007,450,000810,0008,260,000⁦100%⁩
Earthworks & foundations21,240,00013,489,0001,556,00015,045,000⁦71%⁩
Concrete & structural works36,580,00016,926,0002,293,00019,219,000⁦53%⁩
Mechanical, electrical & plumbing28,320,0008,137,0001,331,0009,468,000⁦33%⁩
Finishes & external works17,700,0003,219,000585,0003,804,000⁦21%⁩
Testing & commissioning5,900,000469,00095,000564,000⁦10%⁩
Total118,000,00049,690,0006,670,00056,360,000⁦48%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2026-06-01⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-06-03⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2026-06-06⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-06-09⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-06-12⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-06-01⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2026-06-03⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-06-06⁩

    Eng. Fahad T. Al-Sulami · Director, Regional Qualification Centres

    Took 3 days

  4. Payment order prepared⁦2026-06-09⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-06-12⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-09-29⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

12 June 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-06-12 13:00

9 June 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-06-09 13:00

6 June 2026

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2026-06-06 13:00

3 June 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-06-03 13:00

1 June 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-06-01 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close