Interim payment certificate no. (11)
For the work of September 2026
- Contract number
- SCA/2025/023
- Etimad reference
- 2504720693
- Contract
- Hail vocational qualification centre — construction
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Hail Vocational Qualification Centre
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 118,000,000
- Current contract value
- 118,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 70,000,000 |
| 2 | Less: previous certificates | (64,900,000) |
| 3 | Value of work in this certificate | 5,100,000 |
| 4 | Less: retention (10%) | (510,000) |
| 5 | Less: advance payment recovery (10%) | (510,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,020,000) |
| 8 | Net before VAT | 4,080,000 |
| 9 | Add: value added tax (15%) | 612,000 |
| 10 | Net amount payable to the contractor | 4,692,000 |
Amount in words: Four million six hundred ninety-two thousand Saudi riyals only
Retention held up to this certificate: SAR 7M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 8,260,000 | 7,804,000 | 456,000 | 8,260,000 | 100% |
| Earthworks & foundations | 21,240,000 | 19,449,000 | 1,236,000 | 20,685,000 | 97% |
| Concrete & structural works | 36,580,000 | 22,114,000 | 1,756,000 | 23,870,000 | 65% |
| Mechanical, electrical & plumbing | 28,320,000 | 10,678,000 | 1,082,000 | 11,760,000 | 42% |
| Finishes & external works | 17,700,000 | 4,236,000 | 489,000 | 4,725,000 | 27% |
| Testing & commissioning | 5,900,000 | 619,000 | 81,000 | 700,000 | 12% |
| Total | 118,000,000 | 64,900,000 | 5,100,000 | 70,000,000 | 59% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani