Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 9
- Date
- 2026-07-24
- Hijri
- 10 Safar 1448 AH
- Reference
- PAY-2025-023-09
Interim payment certificate no. (9)
For the work of July 2026
- Contract number
- SCA/2025/023
- Etimad reference
- 2504720693
- Contract
- Hail vocational qualification centre — construction
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Hail Vocational Qualification Centre
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 118,000,000
- Current contract value
- 118,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 61,440,000 |
| 2 | Less: previous certificates | (56,360,000) |
| 3 | Value of work in this certificate | 5,080,000 |
| 4 | Less: retention (10%) | (508,000) |
| 5 | Less: advance payment recovery (10%) | (508,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,016,000) |
| 8 | Net before VAT | 4,064,000 |
| 9 | Add: value added tax (15%) | 609,600 |
| 10 | Net amount payable to the contractor | 4,673,600 |
Amount in words: Four million six hundred seventy-three thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 6.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 8,260,000 | 7,711,000 | 549,000 | 8,260,000 | 100% |
| Earthworks & foundations | 21,240,000 | 15,933,000 | 1,213,000 | 17,146,000 | 81% |
| Concrete & structural works | 36,580,000 | 19,203,000 | 1,748,000 | 20,951,000 | 57% |
| Mechanical, electrical & plumbing | 28,320,000 | 9,286,000 | 1,036,000 | 10,322,000 | 36% |
| Finishes & external works | 17,700,000 | 3,687,000 | 460,000 | 4,147,000 | 23% |
| Testing & commissioning | 5,900,000 | 540,000 | 74,000 | 614,000 | 10% |
| Total | 118,000,000 | 56,360,000 | 5,080,000 | 61,440,000 | 52% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani