Certificate ⁦9⁩ — July 2026

Hail vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
9
Date
⁦2026-07-24⁩
Hijri
10 Safar 1448 AH
Reference
PAY-2025-023-09

Interim payment certificate no. (⁦9⁩)

For the work of July 2026

Contract number
SCA/2025/023
Etimad reference
2504720693
Contract
Hail vocational qualification centre — construction
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
Hail Vocational Qualification Centre
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
118,000,000
Current contract value
118,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date61,440,000
2Less: previous certificates(56,360,000)
3Value of work in this certificate5,080,000
4Less: retention (⁦10%⁩)(508,000)
5Less: advance payment recovery (⁦10%⁩)(508,000)
6Less: delay and breach penalties0
7Total deductions(1,016,000)
8Net before VAT4,064,000
9Add: value added tax (15%)609,600
10Net amount payable to the contractor4,673,600

Amount in words: Four million six hundred seventy-three thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 6.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation8,260,0007,711,000549,0008,260,000⁦100%⁩
Earthworks & foundations21,240,00015,933,0001,213,00017,146,000⁦81%⁩
Concrete & structural works36,580,00019,203,0001,748,00020,951,000⁦57%⁩
Mechanical, electrical & plumbing28,320,0009,286,0001,036,00010,322,000⁦36%⁩
Finishes & external works17,700,0003,687,000460,0004,147,000⁦23%⁩
Testing & commissioning5,900,000540,00074,000614,000⁦10%⁩
Total118,000,00056,360,0005,080,00061,440,000⁦52%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2026-07-24⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-07-26⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2026-07-29⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-08-01⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-08-04⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-24⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2026-07-26⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-07-29⁩

    Eng. Fahad T. Al-Sulami · Director, Regional Qualification Centres

    Took 3 days

  4. Payment order prepared⁦2026-08-01⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-08-04⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-09-29⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

4 August 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-08-04 13:00

1 August 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-08-01 13:00

29 July 2026

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2026-07-29 13:00

26 July 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-07-26 13:00

24 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-24 09:00