SCA/2025/023
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
55% of the current value paid
Paid
64.9Mof a current value of SAR 118M
Value of each certificate
The last 11 — gross and net
Approved: 10
Count: 11 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 11September 2026 | 2026-10-18 | 5.1M | 510K | 510K | 612K | 4.7M | In review | |
| Certificate 10August 2026 | 2026-09-16 | 3.5M | 346K | 346K | 415.2K | 3.2M | Approved | |
| Certificate 9July 2026 | 2026-07-24 | 5.1M | 508K | 508K | 609.6K | 4.7M | Approved | |
| Certificate 8May 2026 | 2026-06-01 | 6.7M | 667K | 667K | 800.4K | 6.1M | Approved | |
| Certificate 7March 2026 | 2026-04-08 | 9M | 897K | 897K | 1.1M | 8.3M | Approved | |
| Certificate 6January 2026 | 2026-02-13 | 7.9M | 792K | 792K | 950.4K | 7.3M | Approved | |
| Certificate 5December 2025 | 2025-12-22 | 9M | 899K | 899K | 1.1M | 8.3M | Approved | |
| Certificate 4October 2025 | 2025-10-29 | 8.6M | 864K | 864K | 1M | 7.9M | Approved | |
| Certificate 3August 2025 | 2025-09-05 | 6.2M | 624K | 624K | 748.8K | 5.7M | Approved | |
| Certificate 2June 2025 | 2025-07-14 | 5.6M | 561K | 561K | 673.2K | 5.2M | Approved | |
| Certificate 1May 2025 | 2025-05-21 | 3.3M | 332K | 332K | 398.4K | 3.1M | Approved |