Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-09-05
- Hijri
- 13 Rabiʻ I 1447 AH
- Reference
- PAY-2025-023-03
Interim payment certificate no. (3)
For the work of August 2025
- Contract number
- SCA/2025/023
- Etimad reference
- 2504720693
- Contract
- Hail vocational qualification centre — construction
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Hail Vocational Qualification Centre
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 118,000,000
- Current contract value
- 118,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 15,170,000 |
| 2 | Less: previous certificates | (8,930,000) |
| 3 | Value of work in this certificate | 6,240,000 |
| 4 | Less: retention (10%) | (624,000) |
| 5 | Less: advance payment recovery (10%) | (624,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,248,000) |
| 8 | Net before VAT | 4,992,000 |
| 9 | Add: value added tax (15%) | 748,800 |
| 10 | Net amount payable to the contractor | 5,740,800 |
Amount in words: Five million seven hundred forty thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 1.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 8,260,000 | 1,475,000 | 974,000 | 2,449,000 | 30% |
| Earthworks & foundations | 21,240,000 | 2,289,000 | 1,534,000 | 3,823,000 | 18% |
| Concrete & structural works | 36,580,000 | 3,041,000 | 2,132,000 | 5,173,000 | 14% |
| Mechanical, electrical & plumbing | 28,320,000 | 1,462,000 | 1,087,000 | 2,549,000 | 9% |
| Finishes & external works | 17,700,000 | 578,000 | 446,000 | 1,024,000 | 6% |
| Testing & commissioning | 5,900,000 | 85,000 | 67,000 | 152,000 | 3% |
| Total | 118,000,000 | 8,930,000 | 6,240,000 | 15,170,000 | 13% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani