Hail Vocational Qualification Centre
Add to watchlistA new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.
Budget (BAC)
Actual cost
53% of budget
Progress
Estimate at completion
SAR +3.2M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-08-10 | 2025-11-04 | +86 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-02 | 2026-05-02 | +151 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-21 | 2026-11-26 | +189 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-07 | 2027-01-28 | +82 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-02-28 | 2027-03-11 | +11 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
52%Awaiting acceptance
11%Not handed in
37%Deliverable flow
Display options
| Project plan & baseline019-D1 | 4% | CRT-019-01 | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-06-15 | V1 | 3 of 3 |
| Monitoring & reporting019-D2 | 4% | CRT-019-02 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-08-10 | V1 | 3 of 3 |
| Detailed design019-D3 | 7% | CRT-019-03 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-10-06 | V1 | 3 of 3 |
| Permits & approvals019-D4 | 7% | CRT-019-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-12-02 | V1 | 3 of 3 |
| Site works & excavation019-D5 | 15% | CRT-019-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-01-27 | V1 | 3 of 3 |
| Structure019-D6 | 15% | CRT-019-06 | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-03-25 | V1 | 3 of 3 |
| Finishes019-D7 | 11% | — | Under review | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-05-21 | V1 | 1 of 3 |
| Supply019-D8 | 9% | — | Draft | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-07-16 | V0 | 0 of 3 |
| Installation019-D9 | 8% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-09-11 | V0 | 0 of 3 |
| Testing & commissioning019-D10 | 8% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-11-07 | V0 | 0 of 3 |
| Provisional acceptance019-D11 | 6% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-01-02 | V0 | 0 of 3 |
| Final acceptance019-D12 | 6% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-02-28 | V0 | 0 of 3 |
| Total · 12 | 100% |