Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 2
- Date
- 2025-07-14
- Hijri
- 19 Muharram 1447 AH
- Reference
- PAY-2025-023-02
Interim payment certificate no. (2)
For the work of June 2025
- Contract number
- SCA/2025/023
- Etimad reference
- 2504720693
- Contract
- Hail vocational qualification centre — construction
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Hail Vocational Qualification Centre
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 118,000,000
- Current contract value
- 118,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 8,930,000 |
| 2 | Less: previous certificates | (3,320,000) |
| 3 | Value of work in this certificate | 5,610,000 |
| 4 | Less: retention (10%) | (561,000) |
| 5 | Less: advance payment recovery (10%) | (561,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,122,000) |
| 8 | Net before VAT | 4,488,000 |
| 9 | Add: value added tax (15%) | 673,200 |
| 10 | Net amount payable to the contractor | 5,161,200 |
Amount in words: Five million one hundred sixty-one thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 893K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 8,260,000 | 554,000 | 889,000 | 1,443,000 | 17% |
| Earthworks & foundations | 21,240,000 | 856,000 | 1,394,000 | 2,250,000 | 11% |
| Concrete & structural works | 36,580,000 | 1,130,000 | 1,915,000 | 3,045,000 | 8% |
| Mechanical, electrical & plumbing | 28,320,000 | 538,000 | 962,000 | 1,500,000 | 5% |
| Finishes & external works | 17,700,000 | 212,000 | 391,000 | 603,000 | 3% |
| Testing & commissioning | 5,900,000 | 30,000 | 59,000 | 89,000 | 2% |
| Total | 118,000,000 | 3,320,000 | 5,610,000 | 8,930,000 | 8% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani