Certificate ⁦2⁩ — June 2025

Hail vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
2
Date
⁦2025-07-14⁩
Hijri
19 Muharram 1447 AH
Reference
PAY-2025-023-02

Interim payment certificate no. (⁦2⁩)

For the work of June 2025

Contract number
SCA/2025/023
Etimad reference
2504720693
Contract
Hail vocational qualification centre — construction
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
Hail Vocational Qualification Centre
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
118,000,000
Current contract value
118,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date8,930,000
2Less: previous certificates(3,320,000)
3Value of work in this certificate5,610,000
4Less: retention (⁦10%⁩)(561,000)
5Less: advance payment recovery (⁦10%⁩)(561,000)
6Less: delay and breach penalties0
7Total deductions(1,122,000)
8Net before VAT4,488,000
9Add: value added tax (15%)673,200
10Net amount payable to the contractor5,161,200

Amount in words: Five million one hundred sixty-one thousand two hundred Saudi riyals only

Retention held up to this certificate: SAR 893K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation8,260,000554,000889,0001,443,000⁦17%⁩
Earthworks & foundations21,240,000856,0001,394,0002,250,000⁦11%⁩
Concrete & structural works36,580,0001,130,0001,915,0003,045,000⁦8%⁩
Mechanical, electrical & plumbing28,320,000538,000962,0001,500,000⁦5%⁩
Finishes & external works17,700,000212,000391,000603,000⁦3%⁩
Testing & commissioning5,900,00030,00059,00089,000⁦2%⁩
Total118,000,0003,320,0005,610,0008,930,000⁦8%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2025-07-14⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-07-16⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2025-07-19⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-07-22⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-07-25⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-07-14⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2025-07-16⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-07-19⁩

    Eng. Fahad T. Al-Sulami · Director, Regional Qualification Centres

    Took 3 days

  4. Payment order prepared⁦2025-07-22⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-07-25⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-10-17⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-05-02⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

25 July 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-07-25 13:00

22 July 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-07-22 13:00

19 July 2025

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2025-07-19 13:00

16 July 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-07-16 13:00

14 July 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-07-14 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close