Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 10
- Date
- 2026-09-16
- Hijri
- 5 Rabiʻ II 1448 AH
- Reference
- PAY-2025-023-10
Interim payment certificate no. (10)
For the work of August 2026
- Contract number
- SCA/2025/023
- Etimad reference
- 2504720693
- Contract
- Hail vocational qualification centre — construction
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Hail Vocational Qualification Centre
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 118,000,000
- Current contract value
- 118,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 64,900,000 |
| 2 | Less: previous certificates | (61,440,000) |
| 3 | Value of work in this certificate | 3,460,000 |
| 4 | Less: retention (10%) | (346,000) |
| 5 | Less: advance payment recovery (10%) | (346,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (692,000) |
| 8 | Net before VAT | 2,768,000 |
| 9 | Add: value added tax (15%) | 415,200 |
| 10 | Net amount payable to the contractor | 3,183,200 |
Amount in words: Three million one hundred eighty-three thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 6.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 8,260,000 | 7,914,000 | 346,000 | 8,260,000 | 100% |
| Earthworks & foundations | 21,240,000 | 17,742,000 | 834,000 | 18,576,000 | 87% |
| Concrete & structural works | 36,580,000 | 20,940,000 | 1,191,000 | 22,131,000 | 61% |
| Mechanical, electrical & plumbing | 28,320,000 | 10,187,000 | 716,000 | 10,903,000 | 38% |
| Finishes & external works | 17,700,000 | 4,061,000 | 320,000 | 4,381,000 | 25% |
| Testing & commissioning | 5,900,000 | 596,000 | 53,000 | 649,000 | 11% |
| Total | 118,000,000 | 61,440,000 | 3,460,000 | 64,900,000 | 55% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani