Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 4
- Date
- 2025-10-29
- Hijri
- 7 Jumada I 1447 AH
- Reference
- PAY-2025-023-04
Interim payment certificate no. (4)
For the work of October 2025
- Contract number
- SCA/2025/023
- Etimad reference
- 2504720693
- Contract
- Hail vocational qualification centre — construction
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Hail Vocational Qualification Centre
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 118,000,000
- Current contract value
- 118,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 23,810,000 |
| 2 | Less: previous certificates | (15,170,000) |
| 3 | Value of work in this certificate | 8,640,000 |
| 4 | Less: retention (10%) | (864,000) |
| 5 | Less: advance payment recovery (10%) | (864,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,728,000) |
| 8 | Net before VAT | 6,912,000 |
| 9 | Add: value added tax (15%) | 1,036,800 |
| 10 | Net amount payable to the contractor | 7,948,800 |
Amount in words: Seven million nine hundred forty-eight thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 2.4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 8,260,000 | 2,528,000 | 1,318,000 | 3,846,000 | 47% |
| Earthworks & foundations | 21,240,000 | 3,912,000 | 2,088,000 | 6,000,000 | 28% |
| Concrete & structural works | 36,580,000 | 5,164,000 | 2,955,000 | 8,119,000 | 22% |
| Mechanical, electrical & plumbing | 28,320,000 | 2,459,000 | 1,541,000 | 4,000,000 | 14% |
| Finishes & external works | 17,700,000 | 966,000 | 641,000 | 1,607,000 | 9% |
| Testing & commissioning | 5,900,000 | 141,000 | 97,000 | 238,000 | 4% |
| Total | 118,000,000 | 15,170,000 | 8,640,000 | 23,810,000 | 20% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani