Certificate ⁦4⁩ — October 2025

Hail vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
4
Date
⁦2025-10-29⁩
Hijri
7 Jumada I 1447 AH
Reference
PAY-2025-023-04

Interim payment certificate no. (⁦4⁩)

For the work of October 2025

Contract number
SCA/2025/023
Etimad reference
2504720693
Contract
Hail vocational qualification centre — construction
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
Hail Vocational Qualification Centre
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
118,000,000
Current contract value
118,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date23,810,000
2Less: previous certificates(15,170,000)
3Value of work in this certificate8,640,000
4Less: retention (⁦10%⁩)(864,000)
5Less: advance payment recovery (⁦10%⁩)(864,000)
6Less: delay and breach penalties0
7Total deductions(1,728,000)
8Net before VAT6,912,000
9Add: value added tax (15%)1,036,800
10Net amount payable to the contractor7,948,800

Amount in words: Seven million nine hundred forty-eight thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 2.4M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation8,260,0002,528,0001,318,0003,846,000⁦47%⁩
Earthworks & foundations21,240,0003,912,0002,088,0006,000,000⁦28%⁩
Concrete & structural works36,580,0005,164,0002,955,0008,119,000⁦22%⁩
Mechanical, electrical & plumbing28,320,0002,459,0001,541,0004,000,000⁦14%⁩
Finishes & external works17,700,000966,000641,0001,607,000⁦9%⁩
Testing & commissioning5,900,000141,00097,000238,000⁦4%⁩
Total118,000,00015,170,0008,640,00023,810,000⁦20%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2025-10-29⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-10-31⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2025-11-03⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-11-06⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-11-09⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-10-29⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2025-10-31⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-11-03⁩

    Eng. Fahad T. Al-Sulami · Director, Regional Qualification Centres

    Took 3 days

  4. Payment order prepared⁦2025-11-06⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-11-09⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-04-22⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

9 November 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-11-09 13:00

6 November 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-11-06 13:00

3 November 2025

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2025-11-03 13:00

31 October 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-10-31 13:00

29 October 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-10-29 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close