Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
- Form no.
- SCA-PMO-F01
- Template edition
- 2.1
- Version
- V2
- Form date
- 2023-08-06
- Hijri
- 19 Muharram 1445 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-002
- Project
- SCA Headquarters, Riyadh
- Portfolio
- Headquarters & Regional Centres Portfolio
- Sector
- Corporate Support Sector
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Ahmed Y. Asiri
1The proposalAuto-filled
- TitleAuto-filled
- SCA Headquarters, Riyadh
- Proposed byAuto-filled
- Eng. Ahmed Y. Asiri
- DepartmentAuto-filled
- Construction Projects Department
- Submitted onAuto-filled
- 2023-08-06
- Proposal numberAuto-filled
- DMD-2026-002
2Justification
A 210,000 m² campus in Al-Malqa housing the Authority’s offices, the contractors’ service hall and the conference & exhibition building in six linked buildings, with multi-storey parking.
3Objectives
- SCA services and programmes in every region
- Build capability and innovation in the sector
Strategic objectives served
- SO-3.1 — SCA services and programmes in every region
- SO-2.1 — Build capability and innovation in the sector
4Expected benefits
| Kind | Benefit |
|---|---|
| No benefits recorded yet | |
5Cost & feasibility
Estimated cost
SAR 1.2B
Funding
The owning sector’s approved budget
| Cost line | Amount |
|---|---|
| Main contract | SAR 849.6M |
| Supervision & consulting | SAR 165.2M |
| Internal team | SAR 106.2M |
| Contingency reserve (5%) | SAR 59M |
| Total | SAR 1.2B |
6Initial risks
| Risk | Level | Proposed response |
|---|---|---|
| Steel and concrete price rises driving price-adjustment claims | High | Treated in the risk management plan |
| Late handover of the northern plot and utility diversions in zones 3 and 4 | High | Treated in the risk management plan |
| Contractor claim for a 120-day extension with compensation | High | Treated in the risk management plan |
| Safety incidents around cranes and deep excavations | Medium | Treated in the risk management plan |
Approval logChain: Proposal & feasibility approval · version 4
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Ahmed Y. AsiriDirector, Construction Projects | Submitted | — | 2023-08-06 10:31 |
| 2 | Line manager endorsement | Technical acceptance | Eng. Reem K. Al-DosariThe requester’s line manager | Approved | — | 2023-08-08 14:41 |
| 3 | PMO review | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2023-08-09 09:48 |
| 4 | Portfolio manager review | Technical acceptance | Eng. Bandar M. Al-ShammariPortfolio manager | Approved | Consistent with the portfolio plan and its priorities. | 2023-08-13 10:55 |
| 5 | Cost & funding review | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2023-08-15 10:07 |
| 6 | Project Approval Committee | Technical acceptance | Dr. Noura M. Al-OtaibiProject Approval Committee | Approved | — | 2023-08-20 12:09 |
Signatures
Line manager endorsement
Eng. Reem K. Al-Dosari
Approved2023-08-08
PMO review
Ghada A. Al-Shahrani
Approved2023-08-09
Portfolio manager review
Eng. Bandar M. Al-Shammari
Approved2023-08-13
Cost & funding review
Munirah A. Al-Khalidi
Approved2023-08-15
Project Approval Committee
Dr. Noura M. Al-Otaibi
Approved2023-08-20