Unified Operations Centre for Centres & Platforms
Add to watchlistA 24/7 operations centre watching the digital platforms, the test halls and the Authority’s buildings in every region.
Budget (BAC)
Actual cost
0% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Pre-startStage 1 of 5
Next gate:Initiation4 November 2026
- Pre-start · Current stagePre-start · Current stage
- Gate into «Initiation»DecisionNot held yetDate4 November 2026Initiation · Not startedInitiation · Not started
- Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2027-06-02 | 2027-06-24 | +22 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-09-26 | 2027-11-03 | +38 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2028-03-17 | 2028-05-19 | +63 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2028-09-06 | 2028-12-03 | +88 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-12-31 | 2029-04-14 | +104 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
0%Awaiting acceptance
0%Not handed in
100%Deliverable flow
Display options
| Project plan & baseline024-D1 | 3% | — | Draft | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Turki A. Al-Anazi | 2027-04-05 | V0 | 0 of 3 |
| Monitoring & reporting024-D2 | 3% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Turki A. Al-Anazi | 2027-06-02 | V0 | 0 of 3 |
| Detailed design024-D3 | 6% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Turki A. Al-Anazi | 2027-07-30 | V0 | 0 of 3 |
| Permits & approvals024-D4 | 6% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Turki A. Al-Anazi | 2027-09-26 | V0 | 0 of 3 |
| Site works & excavation024-D5 | 13% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Turki A. Al-Anazi | 2027-11-23 | V0 | 0 of 3 |
| Structure024-D6 | 13% | — | Draft | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Turki A. Al-Anazi | 2028-01-19 | V0 | 0 of 3 |
| Finishes024-D7 | 12% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Turki A. Al-Anazi | 2028-03-17 | V0 | 0 of 3 |
| Supply024-D8 | 10% | — | Draft | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Turki A. Al-Anazi | 2028-05-14 | V0 | 0 of 3 |
| Installation024-D9 | 10% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Turki A. Al-Anazi | 2028-07-11 | V0 | 0 of 3 |
| Testing & commissioning024-D10 | 10% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Turki A. Al-Anazi | 2028-09-06 | V0 | 0 of 3 |
| Provisional acceptance024-D11 | 7% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Turki A. Al-Anazi | 2028-11-03 | V0 | 0 of 3 |
| Final acceptance024-D12 | 7% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Turki A. Al-Anazi | 2028-12-31 | V0 | 0 of 3 |
| Total · 12 | 100% |