Project status card
28 October 2026 · 17 Jumada I 1448 AH
Al-Jouf Training Centre Rehabilitation
PRJ-2026-025 · Corporate Support Sector · Operational · WP-2025-025
- Progress
- 36% / 35%
- SPI · CPI
- 1.03 · 1.02
- Spend
- SAR 14.8M / SAR 42M
- Estimate at completion
- SAR 41.2M
Schedule
Planned to date 35%
Forecast finish: 2027-09-3029 Rabiʻ II 1449 AH · On time
SPI1.03Schedule performance index · 1.03CPI1.02Cost performance index · 1.02Health dimensions
Last update: 2026-10-2615 Jumada I 1448 AH · Up to date
Deliverables
5 of 6 due deliverables accepted on time (83%)
Next milestones
- Build complete2027-02-0629 Shaʻban 1448 AH
- Testing & acceptance complete2027-06-3025 Muharram 1449 AH
- Final handover2027-10-044 Jumada I 1449 AH
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 42M: 1 on track and 0 red or critical. Weighted progress is 36% against 35% planned, spend SAR 14.8M, and EAC SAR 41.2M (SAR 0.8M under).
No project is more than a month behind baseline.