Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-025On track4ExecutionConstruction

Al-Jouf Training Centre Rehabilitation

Add to watchlist

Rehabilitating the training centre building in Sakaka — halls, MEP systems and accessible entrances.

Budget (BAC)

SAR 42M

Actual cost

SAR 14.8M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 41.2M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-03-16⁩
Hijri
16 Ramadan 1446 AH
ApprovedDMD-2026-025Al-Jouf Training Centre Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-025
Project
Al-Jouf Training Centre Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Mishari K. Al-Otaibi

1The proposalAuto-filled

TitleAuto-filled
Al-Jouf Training Centre Rehabilitation
Proposed byAuto-filled
Eng. Mishari K. Al-Otaibi
DepartmentAuto-filled
Sustainability & Energy Efficiency Department
Submitted onAuto-filled
⁦2025-03-16⁩
Proposal numberAuto-filled
DMD-2026-025

2Justification

Rehabilitating the training centre building in Sakaka — halls, MEP systems and accessible entrances.

3Objectives

  1. Efficient, sustainable SCA facilities
  2. A better contractor experience and service quality

Strategic objectives served

  • SO-3.2 — Efficient, sustainable SCA facilities
  • SO-3.3 — A better contractor experience and service quality

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 42M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 30.2M
Supervision & consultingSAR 5.9M
Internal teamSAR 3.8M
Contingency reserve (5%)SAR 2.1M
TotalSAR 42M

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencySubmitted—⁦2025-03-16⁩ 09:06
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-03-17⁩ 13:46
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-03-20⁩ 14:53
4Portfolio manager reviewTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-03-23⁩ 09:00
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-03-26⁩ 09:42
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-03-31⁩ 11:14

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-03-17⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-03-20⁩

Portfolio manager review

Eng. Mishari K. Al-Otaibi

Approved⁦2025-03-23⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-03-26⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-03-31⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2025-03-16⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-03-17⁩ at ⁦13:46⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-03-20⁩ at ⁦14:53⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2025-03-23⁩ at ⁦09:00⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-03-26⁩ at ⁦09:42⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-03-31⁩ at ⁦11:14⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-04-06⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Mishari K. Al-Otaibi

  2. V1Returned for edit⁦2025-03-16⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Mishari K. Al-Otaibi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close