PRJ-2026-025On track4ExecutionConstruction

Al-Jouf Training Centre Rehabilitation

Add to watchlist

Rehabilitating the training centre building in Sakaka — halls, MEP systems and accessible entrances.

Budget (BAC)

SAR 42M

Actual cost

SAR 14.8M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 41.2M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
SCA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2025-05-10⁩
Hijri
12 Dhuʻl-Qiʻdah 1446 AH
ApprovedPRJ-2026-025Al-Jouf Training Centre Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-025
Project
Al-Jouf Training Centre Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Mishari K. Al-Otaibi

1The resultAuto-filled

Priority score

70 of 100

Class

P2

60–74

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the SCA strategy⁦20%⁩4.718.5
Value added to the contracting sector⁦12%⁩4.29.6
Financial return & sustainability⁦8%⁩3.85.6
Urgency⁦10%⁩3.56.3
Regulatory requirement⁦10%⁩1.61.5
Risk⁦7%⁩2.05.3
Complexity⁦6%⁩1.94.7
Resource requirement⁦5%⁩1.54.4
Impact on contractors & beneficiaries⁦14%⁩4.010.5
Sustainability impact⁦3%⁩4.52.6
Digital transformation impact⁦5%⁩1.91.1
Total⁦100%⁩—70

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2025-05-10⁩ 10:31
2Evaluation checked against the modelMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-05-12⁩ 14:05
3Portfolio manager reviewTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApproved—⁦2025-05-13⁩ 09:12
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-05-18⁩ 10:19

Signatures

Evaluation checked against the model

Ghada A. Al-Shahrani

Approved⁦2025-05-12⁩

Portfolio manager review

Eng. Mishari K. Al-Otaibi

Approved⁦2025-05-13⁩

Class approved — Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-05-18⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2025-05-10⁩

  1. Methodology review

    Evaluation checked against the model

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-05-12⁩ at ⁦14:05⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2025-05-13⁩ at ⁦09:12⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-05-18⁩ at ⁦10:19⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2025-05-10⁩

    Evaluated on the approved priority model

    Ghada A. Al-Shahrani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close