1.03Schedule performance index · 1.031.02Cost performance index · 1.02
Forecast finish
2027-09-30
On baseline
Execution·Stage 4 of 5
Next gate:Closure4 August 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+4 days vs approved
Baseline (original = approved)2027-09-30
Current forecast2027-10-04
By earned schedule2028-05-28
Critical activities
8
of 10 open activities
Late activities
7
past their baseline finish
Schedule performance
0.64
earned ÷ planned value
Next milestone
in 101 days
Build complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
2028
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Today
2027-10-0436%
Al-Jouf Training Centre RehabilitationPlanned: 2025-10-12 → 2027-09-30Forecast: 2025-10-12 → 2027-10-04Float: 0d