Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-028On track4ExecutionWaterfall

SCA Strategy Refresh & Execution Plans

Add to watchlist

Turning the four axes and 34 initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-07-12⁩
Hijri
27 Muharram 1448 AH
ApprovedCRT-028-02Monitoring & reporting

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-028
Project
SCA Strategy Refresh & Execution Plans
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Abeer H. Al-Shamrani

1The deliverableAuto-filled

DeliverableAuto-filled
Monitoring & reporting
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Dr. Amal F. Al-Sudairi
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦6%⁩
DueAuto-filled
⁦2026-06-27⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-028_1.2_v1.pdfV1Dr. Amal F. Al-Sudairi⁦2026-05-30⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Dr. Amal F. Al-Sudairi
Accepted byAuto-filled
Dr. Mohammed I. Al-Subaie
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2026-003
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dr. Amal F. Al-SudairiDirector General, Strategy & PerformanceSubmitted—⁦2026-05-30⁩ 09:00
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-05-31⁩ 11:08
3Inspection & technical acceptance — ownerTechnical acceptanceDr. Mohammed I. Al-SubaieProject ownerOn behalf of Dr. Amal F. Al-SudairiApprovedInspected and accepted against the approved acceptance criteria.⁦2026-06-01⁩ 12:15
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-06-03⁩ 12:15
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-06-04⁩ 13:52

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2026-05-31⁩

Inspection & technical acceptance — owner

Dr. Mohammed I. Al-Subaie

Approved⁦2026-06-01⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-06-03⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-06-04⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Dr. Amal F. Al-Sudairi on ⁦2026-05-30⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-05-31⁩ at ⁦11:08⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2026-06-01⁩ at ⁦12:15⁩ · On behalf of Dr. Amal F. Al-Sudairi (Dr. Mohammed I. Al-Subaie)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-06-03⁩ at ⁦12:15⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-06-04⁩ at ⁦13:52⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-05-30⁩

    PRJ-2026-028_1.2_v1.pdf

    Dr. Amal F. Al-Sudairi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close