PRJ-2026-028On track4ExecutionWaterfall

SCA Strategy Refresh & Execution Plans

Add to watchlist

Turning the four axes and 34 initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Saudi Contractors Authority

Project charter

SCA Strategy Refresh & Execution Plans

APPROVEDV2Approved ⁦2026-05-01⁩

1Project identity

Required at this stage
Project name
SCA Strategy Refresh & Execution Plans
Project code
PRJ-2026-028
Project sponsor
Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.sa
Project manager
Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@sca.sa
Project owner
Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.sa
Portfolio & programme
Institutional Excellence & Governance PortfolioInstitutional Excellence & Capability Programme
Type & methodology
Consulting · Waterfall
Current phase
4Execution

2Background & rationale

Required at this stage

Turning the four axes and ⁦34⁩ initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision ⁦2030⁩.

3Objectives

Required at this stage
  1. 1A mature operating model and accountability

4Scope

Required at this stage

In scope

  • Turning the four axes and ⁦34⁩ initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision ⁦2030⁩.
  • An approved method
  • Workshops with every sector

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1An approved method
  2. 2Workshops with every sector
  3. 3Knowledge transfer to the internal team

6Deliverables

Required at this stage
1Project management plan⁦2026-05-12⁩
2Main deliverable — stage 1⁦2026-08-26⁩
3Main deliverable — final stage⁦2026-11-13⁩
4Final report⁦2026-12-15⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2026-05-01⁩
  2. Contract signed⁦2026-06-08⁩
  3. 50% of works complete⁦2026-08-26⁩
  4. Provisional acceptance⁦2026-11-27⁩
  5. Closure⁦2026-12-15⁩

8Budget

Required at this stage
  • Main contract⁦71.9%⁩2.3M
  • Supervision & consulting⁦12.5%⁩400K
  • Internal team⁦9.4%⁩300K
  • Contingency reserve (⁦5%⁩)⁦6.3%⁩200K
The owning sector’s approved budgetTotal3.2M

9Timeline

Required at this stage
Start
2026-05-0316 Dhuʻl-Qiʻdah 1447 AH
Baseline finish
2026-12-156 Rajab 1448 AH
Duration
⁦7⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

Required at this stage
  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board