PRJ-2026-028On track4ExecutionWaterfall

SCA Strategy Refresh & Execution Plans

Add to watchlist

Turning the four axes and 34 initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

Draft
Progress
⁦70%⁩
Planned
⁦68%⁩
SPI
1.03
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-028-2026-10Draft⁦70%⁩—⁦2026-10-26⁩
September 2026UPD-028-2026-09Approved⁦66%⁩—⁦2026-10-02⁩
August 2026UPD-028-2026-08Approved⁦62%⁩—⁦2026-09-02⁩