PRJ-2026-028On track4ExecutionWaterfall

SCA Strategy Refresh & Execution Plans

Add to watchlist

Turning the four axes and 34 initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2026-05-28⁩
Hijri
11 Dhuʻl-Hijjah 1447 AH
ApprovedPRJ-2026-028SCA Strategy Refresh & Execution Plans

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-028
Project
SCA Strategy Refresh & Execution Plans
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Abeer H. Al-Shamrani

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2026-05-03⁩

Baseline finish

⁦2026-12-15⁩

Forecast finish

⁦2026-12-15⁩

SPI

1.03

MilestonePlannedForecastSlip
Project plan approved⁦2026-06-27⁩⁦2026-07-12⁩+15 days
Designs approved⁦2026-08-09⁩⁦2026-09-04⁩+26 days
Build complete⁦2026-09-21⁩⁦2026-10-26⁩+35 days
Testing & acceptance complete⁦2026-11-02⁩⁦2026-11-22⁩+20 days
Final handover⁦2026-12-15⁩⁦2026-12-15⁩0

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦6%⁩⁦2026-06-06⁩Abeer H. Al-Shamrani
Monitoring & reporting⁦6%⁩⁦2026-06-27⁩Dr. Amal F. Al-Sudairi
Current-state assessment⁦12%⁩⁦2026-07-19⁩Dr. Amal F. Al-Sudairi
Benchmarking⁦12%⁩⁦2026-08-09⁩Dr. Mohammed I. Al-Subaie
Target model⁦17%⁩⁦2026-08-30⁩Dr. Mohammed I. Al-Subaie
Roadmap⁦17%⁩⁦2026-09-21⁩Abeer H. Al-Shamrani
Wave 1⁦11%⁩⁦2026-10-12⁩Abeer H. Al-Shamrani
Wave 2⁦11%⁩⁦2026-11-02⁩Dr. Amal F. Al-Sudairi
Knowledge transfer⁦4%⁩⁦2026-11-24⁩Dr. Amal F. Al-Sudairi
Final report⁦4%⁩⁦2026-12-15⁩Dr. Mohammed I. Al-Subaie
Accepted with a certificate⁦70%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyAbeer H. Al-Shamrani
Project ownerDeliverable status and acceptance datesFortnightlyAbeer H. Al-Shamrani
PMOData and indicator updatesWeeklyAbeer H. Al-Shamrani
BeneficiariesWhat changes and whenAt each milestoneAbeer H. Al-Shamrani
Team memberRoleAllocation
Abeer H. Al-ShamraniProject manager⁦70%⁩
Dr. Mohammed I. Al-SubaieProject sponsor⁦25%⁩
Dr. Noura M. Al-OtaibiGovernance adviser to the strategy refresh⁦10%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Abeer H. Al-ShamraniHead of Strategy ManagementSubmitted—⁦2026-05-28⁩ 14:59
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2026-06-01⁩ 10:01
3Technical acceptance — project ownerTechnical acceptanceDr. Amal F. Al-SudairiProject ownerApproved—⁦2026-06-04⁩ 11:08
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-06-07⁩ 09:54
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-06-09⁩ 10:31
6Sponsor approvalTechnical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2026-06-14⁩ 14:29

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2026-06-01⁩

Technical acceptance — project owner

Dr. Amal F. Al-Sudairi

Approved⁦2026-06-04⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2026-06-07⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2026-06-09⁩

Sponsor approval

Dr. Mohammed I. Al-Subaie

Approved⁦2026-06-14⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Abeer H. Al-Shamrani on ⁦2026-05-28⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-06-01⁩ at ⁦10:01⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2026-06-04⁩ at ⁦11:08⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-06-07⁩ at ⁦09:54⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-06-09⁩ at ⁦10:31⁩

  5. Technical acceptance

    Sponsor approval

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2026-06-14⁩ at ⁦14:29⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-05-28⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Abeer H. Al-Shamrani

  2. V1Returned for edit⁦2026-05-14⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Abeer H. Al-Shamrani

Esc